Germany

First Tunnel driven for the Düsseldorf Wehrhahn Line

The Wehrhahn Line, a 300 mill. euro project is intended to relieve traffic in the centre of Düsseldorf considerably once it is opened in 2015. The 3.4 km long Underground line will replace a number of tram lines on the surface. Towards this end roughly 2.3 km of tunnel tubes with 8.30 m internal diameter are to be bored by mechanised means for 2 directional tracks –one after the other in 2 single drives (1,290/955 m) using the same 65 m long and roughly 1,300 t heavy TBM with bentonite-supported face, a mix-shield with 9.49 m diameter (S-491 from the Herrenknecht AG).

The first section of tunnel embraces the bore from the Bilk access shaft to the target shaft at the Benrather Straße Underground Station and largely runs beneath the urban area. The TBM was able to break through in late-September 2010 in less than 7 months – a month ahead of schedule. The shield was then dismantled and returned to the access shaft at the Corneliusplatz and reassembled there to drive the second tunnel section. The TBM backup was pulled back through the bored tunnel to the Bilk access shaft, dismantled and also transported to the access shaft at Corneliusplatz. Starting from that point the second tunnel section will be produced with the TBM heading to the target shaft Am Wehrhahn, which partially runs beneath existing buildings and partially under the road grid.

The tunnel is to be lined with reinforced concrete segments (45 cm) in 1.5 m wide rings (7+1/ring) with conic keystone, cam and groove couplings and external sealing strip. The method selected to construct the tunnel sections as well as the underground stations contributes towards ensuring that traffic is hampered as little as possible during the construction phase. ⇥G. B.


Related articles:

04/2012 Germany

Second Tunnel Section for the Düsseldorf Wehrhahn Line driven

The Wehrhahn Line, a 300 million euro Metro project, is intended to relieve traffic in downtown Düsseldorf once it opens in 2015, for it will replace several tram routes operating on the surface. For...

more
08/2014 Austria?/?Brenner Base Tunnel

Completion of Ventilation Shaft

Both during the construction phase as well as during subsequent rail operations of the Brenner Base Tunnel, the ventilation shaft at the community of Patsch together with the ventilation cavern will...

more
03/2010 Germany

The Hirschhagen Tunnel approved

The plan approval decision for the construction section from Helsa-East to Hessisch Lichtenau-West of the A44 motorway also marks work starting on the 4.1 km long Hirschhagen Tunnel, the longest on...

more
03/2010 Switzerland

Intermediate Financing for the Zurich DML

The Zurich cross-city link (DML) embraces the new Zurich-Alstetten – Hauptbahn-hof – Zurich-Oerlikon railway route, the 4-track underground through station Löwenstraße as well as the extension and...

more
05/2012 Switzerland

East Section of Biel Bypass: Breakthrough at Längholz Tunnel

One of the final gaps in the Swiss motorway network is to be closed with the Biel Bypass in the Canton of Berne. The project will link the T6 from Berne with the A16 and A5 and is split into 2...

more