Germany

First Tunnel Boring Machine approved for Rastatt Tunnel

The first of two tunnel boring machines (TBMs) for the Rastatt Tunnel by manufacturer Herrenknecht was approved by the customer, the Tunnel Rastatt JV, on December 8, 2015 at the factory in Schwanau. The two mix-shields will each tackle a bore of the twin-tube tunnel completing them in carcass state. The rail tunnel is part of the new/upgraded Karlsruhe–Basle rail link.

The 93 m long mix-shield S-953 with a weight of 2300 t, a shield diameter of 10.94 m and a cutting wheel output of 1820 kW is now being dismantled and transported to the access pit at Ötigheim. Once reassembled, the machine will...

Find out more in the current Issue. Order now.

Related articles:

02/2012 Germany

Building the Rastatt Tunnel

A tunnel is to be produced in Rastatt after all in conjunction with the 4-track upgrading of the Rheintal railway. It will undercut the entire bounds of the city as well as the Federbach lowland area...

more
06/2013 Book Review

The Katzenberg Tunnel

Upgraded and new Karlsruhe-Basle Route, Issued by: DB ProjektBau GmbHm 2012, 120 pp. (210x297 mm) with 110 Ill. /Tab. and 20 Sources, ISBN 978-3-7771-0450-8, bound € 38.-, DVV Media Group GmbH,...

more
03/2013 Germany

Katzenberg Tunnel operational

The 8,385 m long Katzenberg Tunnel was opened after 9 years of construction when the timetable changed on December 9, 2012. A few days previously 2 trains, an ICE and a goods train, passed parallel...

more
08/2014 Germany

Rastatt Tunnel commissioned

The Rheintalbahn (Rhine Valley Railway) is one of Germany’s busiest rail routes. It is extended on to four tracks mainly for the requirements of freight traffic running between the container ports in...

more
08/2012 Germany

Financing of Rastatt Tunnel

The urgently needed upgrading of the Rhine Valley rail route is forging ahead. The Federal Ministry for Transport, Building and Urban Development and the Deutsche Bahn AG have reached agreement on...