Formwork Technology

Underwater tunnel Limerick in Ireland

As part of the new M7 motorway development in the southwest of Ireland, the 4-lane route crosses the Shannon near Limerick, a few km before the river flows directly into the Atlantic. Centrepiece of the 10  km long “Limerick Southern Ring Road” is the required tunnelling with a length of 675  m. Including the north and south entrance and exit ramps, the tunnel measures a total of 915  m. Completion of the around 10  km  long section and the Shannon tunnel is planned for autumn 2010.

Formwork Solution
Formwork and scaffolding specialist, Peri, provided 2 different tailored tunnel formwork...

Related articles:

Issue 06/2011 Gotthard Base Tunnel

Fully-hydraulic Forming for complex Tunnel Cross-Section

In the Gotthard Base Tunnel’s Erstfeld section a fully hydraulic and flexibly adjustable tunnel forming carriage served to execute the inner shell for 2 branching structures, which tapered greatly in...

more
Issue 06/2009 Formwork Technology

Stable Tunnel Formwork Carriage with flexible Design

A large number of infrastructural schemes are being executed in the region for the 2014 Winter Olympics to be held in the Black Sea resort of Sochi. These include a roughly 13??km long bypass for the...

more
Issue 01/2023 Formwork Technology

Fully Hydraulic Crawler Driven Formwork Carriage for Varying Tunnel Cross-Sections

Since May 2020, tunnel construction work has been underway to the north and south of the Danube for the future accesses and exits of the suspension bridge. Five different tunnel cross-sections, the...

more
USA

State Route 99 Tunnel: Formwork Solution for Double-Deck Tunnel

A Replacement for the Alaskan Way Viaduct After the Alaskan Way Viaduct had suffered considerable damage due to a major earthquake in 2001, initial preparations were made for a replacement. Eight...

more
Issue 02/2010 Formwork Technology

Self-propelled Formwork Car for Tunnel driven by Mining Means

Bypassing the centre of the town of Neckargemünd represents the most extensive project on a county road in the history of the Rhein-Neckar District – work has been in progress here since 1999....

more