Egypt

Four Breakthroughs for Road Tunnels under the Suez Canal

On the 2017 Christmas weekend, Egyptian President Abdel Fattah al-Sisi inaugurated very significant development projects at the Suez Canal. These included two gigantic twin-tube road tunnels under the international trading artery. A total of four tunnel tubes were driven in about 1.5 years for the new, efficient transport links under the artificial waterway. The shells are now almost completed: two road tunnels were built north of Ismailia and run under the old and new Suez Canal. Two more cross beneath the canal south of Port Said.

With this key large-scale project, Egypt is expanding its infrastructure. The efficient connection of the canal cities to the waterway's eastern shore will simplify trade activities, facilitate traffic and support economic development of the region.

 

Four Breakthroughs within one Month

On December 23, 2017, the third Herrenknecht Mixshield S-960, with a diameter of 13.02 m, completed the final drive for the road tunnel project at Ismailia on the Suez Canal. For the new Suez crossings, president al-Sisi ordered a total of four identical tunnel boring machines (TBMs S-958–S-961) from Herrenknecht. Under the direction of the construction companies Joint Venture Arab Contractors/Orascom and Joint Venture Petrojet/Concord/CMC, in the past 19 months these giant tunnelling machines produced the tunnels near the Egyptian cities of Ismailia and Port Said at depths of up to 60 m and at a water pressure of up to 6 bar. All in all, the high-tech machines from Schwanau bored and built 15.3 km of new tunnel during this time.

To allow for a smooth project progress during the very complex tunnel operations, Herrenknecht AG trained 40 Egyptian engineers in Schwanau and on the jobsites. For optimal support of the tunnelling processes, Herrenknecht also provided the tunnelling teams with comprehensive services and supplied key peripheral equipment through the Herrenknecht subsidiaries VMT, MSD, Formwork, H+E and TMS.

The road tunnel in Ismailia reach has a length of 4.8 km and with a 10.6 m inner diameter. Each tube will have two 3.75 m wide lanes for vehicles. The twin-tube road tunnel in Port Said has the same geometrical parameters, the only difference is its length of 2.8 km.

The TBM drives for the construction of the four tunnel bores started with the first of the Ismailia bores in November 2015. This TBM (S-958) achieved breakthrough on 3 December 2017. The next TBMs followed in a 1–2 week break through rhythm on 14 December 2017 (S-959), 23 December 2017 (S-960) and the last on 4 January 2018 (S-961).

Egypt's President al-Sisi and Dr.-Ing. E.h. Martin Herrenknecht, Chairman of the Board of Management of Herrenknecht AG, were personally present at the final TBM breakthrough of the Mixshield S-960 at Ismailia. Al-Sisi emphasized that the project was crucial to Egypt's future. The previously neglected economy of Sinai Peninsula can grow as a result. The tunnels will shorten the time for crossing the Suez Canal immensely: currently this can take up to five days, as queues of traffic to the ferry back up for miles. With the new tunnel connections, soon it will take only 10 minutes.


Related articles:

01/2018 Egypt

Four Breakthroughs for Road Tunnels under the Suez Canal

On the 2017 Christmas weekend, Egyptian President H.E. Abdel Fattah al-Sisi inaugurated very significant development projects at the Suez Canal. These included two gigantic twin-tube road tunnels...

more
05/2018

Tunnelling under the Suez Canal in Port Said

Within the scope of the Masterplan dating from 2014, the projects in Ismailia and Port Said, which are located at the Suez Canal, were executed almost simultaneously. As a result, two road tunnels,...

more
02/2015

Herrenknecht

On the occasion of the World Tunnel Congress Herrenknecht presents itself as the pioneer in mechanized tunnelling. Using Herrenknecht Tunnelling Systems, modern tunnels worldwide are created safe and...

more
05/2015 Austria

Gleinalm Tunnel: Second Bore broken through

After more than a year of tunnelling, the second bore of the 8320 m long Gleinalm Tunnel, the third longest road tunnel in Austria, was broken through in the middle of 2015. After the planned...

more
02/2017 Compendium

Tunnelling Manual 2017

For more than 40 years this pocketbook has been a practice-oriented guide for clients, planners and contractors. It tackles topical developments and provides solutions to problems while at the same...

more