2nd Munich S-Bahn Main Line: Status of Construction Work on the West Tunnel and at the Central Station

Preparatory work in the western section is in full swing and rescue shaft RS 3 has been completed. Work has begun on excavating the final level E-6 in the central access structure at the Central Station (Fig. 1). Following the presentation of the 2nd S-Bahn Main Line in tunnel 2/2023 and the joint venture ARGE Tunnel Hauptbahnhof (ATH) in tunnel 5/2023 and tunnel 6/2024, the following article provides an up-to-date overview of the progress of work in the west and at the main station.

1 Launch Pit and Exploratory Tunnel West of the Main Station

The western section contains the approximately 200 m long launch pit for the tunnel boring machines for the exploratory tunnel and the two traffic tunnels. Of this, 80 m will remain open after construction. The structure is sealed off to the east, and the launch pit has been partially backfilled to the level of the exploratory tunnel for the start of its excavation (Fig. 2). Demolition work is also largely carried out via the launch pit. The temporary floor slab and concrete support structures for the launch of the TBMs for the...

Related articles:

Issue 06/2024

2nd Munich S-Bahn Main Line: Construction Progress on the West Tunnel and at the Central Station

In April 2024, tunnel construction for the 2nd S-Bahn main line began with a symbolic start at the up to 34 m deep RS3 rescue shaft in Munich‘s Arnulfpark. ARGE ATH made the following progress in the...

more
Issue 05/2023

Tunnel Construction West and Main Station in Munich: Current Status of Ongoing Works

The lot of award unit 30 (VE 30) starts in the west after Laim Station with the starting shaft for the TBM in front of the Donnersberger Bridge and ends with tunnel construction at the Marienhof...

more
Issue 05/2023

2nd Munich S-Bahn Main Line: Tender for the Eastern Section Until the End of 2023

Starting at Marienhof, award unit 733 (VE 733, Fig. 1) comprises the construction of the two traffic tunnel tubes with cross passages and intermediate exploration and rescue tunnel (ERS), rescue...

more
Issue 05/2024

Breakthrough and Launch Ceremony at the Brenner Base Tunnel

Of the tunnel system, which is over 220 km long in total, 180 km have currently been driven – 80 km of which are main tunnels, 56 km exploratory tunnels and 44 km access, rescue and logistics...

more
Issue 02/2012 Switzerland

Handeck-Gerstenegg Exploratory Tunnel

Currently the Handeck-Gerstenegg exploratory tunnel is under construction to secure access in winter to the Grimsel 1 and 2 power plants as well as to open up  further “KWO plus” projects for the...

more