Switzerland | Schweiz

Gotthard Base Tunnel Fully Operational Again

As of September 2, 2024, the Gotthard Base Tunnel is once again fully open to rail traffic. Almost 13 months after the derailment of a freight train on 10 August 2023, the world‘s longest railroad tunnel (57 km) is now back to full capacity.

The damage caused by the derailment of the freight train in the Gotthard Base Tunnel was serious. SBB currently estimates the amount of damage, including loss of earnings, at around 150 million swiss francs. Around 140 million swiss francs thereof are likely to be insured. The estimation accuracy for both figures is +/- 20 percent.

Due to the extent of the damage, it took around one and a half months to clear the tunnel. During the repair work, around seven kilometers of the roadway had to be completely renewed, i.e. the rails were replaced, as were over 20 000 sleeper blocks and the concrete layer in which they are cast. In addition, the track change gate, two high-speed switches and many other safety and operationally relevant system components were replaced.

x

Related articles:

Switzerland

Gotthard Base Tunnel Fully Operational Again

The damage caused by the derailment of the freight train in the Gotthard Base Tunnel was serious. SBB currently estimates the amount of damage, including loss of earnings, at around 150 million swiss...

more
Switzerland

Derailment Detectors on the Approaches to the Gotthard Base Tunnel Are in Operation

The detectors have been installed on a particularly sensitive section before the portal cross-over points on the access lines to the Gotthard Base Tunnel. Both passenger and freight trains travel at...

more
Switzerland

Gotthard Base Tunnel: Clearing and Rescue Operations Will Last Until End of September 2023

No Official Information Yet on Cause of Derailment and Extent of Damage The incident in the Gotthard Base Tunnel occurred in the early afternoon at the Faido multifunction station. The freight train...

more
Issue 08/2010 Switzerland

Gotthard Base Tunnel: First bore completion breakthrough in world‘s longest rail tunnel

The world‘s longest rail tunnel is coming ever closer to reality: the first bore completion breakthrough in the Gotthard Base Tunnel took place in the eastern bore on October 15, 2010, 30 km from...

more
Issue 08/2015 Switzerland

Test Operation in the Gotthard Base Tunnel

Since early October 2015, the test operation phase in the Gotthard Base Tunnel has been in full swing. Numerous test runs have already been performed. Until May 31, 2016, around 5000 test runs are...

more