Denmark/Germany

Preparations for Immersing Tunnel Elements Into the Fehmarnbelt

According to information from the project company Femern A/S, preparations for the special ship IVY, which plays a key role in the construction of the Fehmarnbelt Tunnel, were nearing completion at the end of January 2026.The approval of the immersion pontoon is almost two years behind the original schedule.

According to information from the project company Femern A/S, preparations for the special ship IVY were nearing completion at the end of January 2026
Credit/Quelle: Femern A/S

According to information from the project company Femern A/S, preparations for the special ship IVY were nearing completion at the end of January 2026
Credit/Quelle: Femern A/S
The first part of the tunnel trench is currently being prepared for immersion. The trench is being adapted to the elements, and the contractor is laying a gravel bed to create an even base for the tunnel elements.

“We are in direct negotiations with the senior management of the large construction companies that will build the tunnel. Our focus is on resolving the current challenges and finding solutions that will drive the project forward,” says Mikkel Hemmingsen, CEO of Sund & Bælt, the owner of the Fehmarnbelt Tunnel.

15 Tunnel Elements Have Been Cast

To date, 15 tunnel elements have been cast in the factory on Lolland, corresponding to the first 2.7 kilometres of the tunnel. The contractor expects the first element to be immersed in spring 2026. The delay in immersion is such that it is no longer realistic to open the link in 2029.

Special Vessel „Hebo Lift 9“

Furthermore, at the end of January 2026 a new special vessel has arrived in the work harbour in Rødbyhavn. It is the large floating crane “Hebo Lift 9”. The floating crane will place the enormous anchors on the seabed, to which the immersion pontoon IVY will be attached with long steel wires in connection with the immersion of the first tunnel element this spring.

A total of eight anchors weighing 500 t each will be used. The anchors are shaped like large boxes and are lowered onto the seabed. After the immersion of an element, the anchors can then be picked up again by the crane and reused in connection with the immersion of the next element. “Hebo Lift 9” can easily handle the weight, as it can lift up to 800 t. The crane can lift to a height of 67 m and the vessel is 27 m wide.

New Overall Schedule for the Entire Project

Sund & Bælt will prepare a new overall schedule for the entire project after the first tunnel elements have been immersed. The delay will also have an impact on the total construction costs of the project.

Like the previous infrastructure projects realised by Sund & Bælt – the Storebælt and Øresund links – the Fehmarnbelt Tunnel will also be user-financed and based on loans that are repaid from traffic revenue. An expected delay and increase in costs will therefore only affect the repayment period.

The overall project will still be able to be implemented as a user-financed project. The repayment period for the tunnel and the Danish land facilities is expected to remain within the framework of the Danish Construction Act.

x

Related articles:

Issue 02/2026 Denmark

Fehmarnbelt Tunnel: Special Vessel IVY Undergoes Final Tests

The immersion pontoons are currently located in the large Danish work harbour on Lolland, with the first tunnel element secured between the two units. The initial phase of testing has already been...

more
Issue 02/2026 Denmark | Dänemark

Fehmarnbelt Tunnel: Special Vessel IVY Undergoes Final Tests

The special vessel that will be used to lower the tunnel segments for the Fehmarnbelt Tunnel is currently undergoing final tests at the working harbour near Rødbyhavn ahead of certification by the...

more
Denmark

Fehmarnbelt Tunnel: 10 000 Tons of Special Formwork Delivered

After its planned completion in 2029, the Fehmarnbelt Tunnel will connect Denmark and Germany for road and rail traffic. The immersed tunnel with a total width of 45 m consists of concrete elements...

more
Issue 01/2026 Denmark | Dänemark

Fehmarnbelt Tunnel: Tower Cranes on Rails Support Production of Concrete Elements

State-of-the-art Liebherr crane technology is being used in the construction of the Fehmarn Belt Tunnel, one of the largest infrastructure projects in Northern Europe. The Femern Link Contractors...

more
Denmark/Germany

Doka Has Been Awarded Contract for Fehmarnbelt Tunnel

The fixed link across the Fehmarnbelt is an important contribution to the transformation of mobility in Europe. The almost 18 km long tunnel leads from Rødbyhavn on Lolland in Denmark to Puttgarden...

more