Germany

New Railway Line Gelnhausen–Fulda: 28 km of the Route will run in Tunnels

Longest tunnel on this line planned to run over a distance of 9.5 km

After weighing the advantages and disadvantages, German Railways (DB) announced a preference for a new line between Gelnhausen and the Fulda–Würzburg high-speed line at the Dialogforum Hanau–Würzburg/Fulda on 15 June 2018 and will apply for this so-called “Variant IV” in a planning approval process in early 2019.

Thanks to the high proportion of tunnels of about 28 km out of the total line distance of 44 km, the line of Variant IV will have little impact on people and environment and will above all relieve the towns and villages in the Kinzigtal from the noise of goods traffic.

The longest tunnel on this line is planned to run over a distance of 9.5 km between Schlüchtern and Mittelkalbach. For passenger services, the journey time between Frankfurt am Main and Fulda will be shortened by eleven minutes. A link to the existing line is provided in Schlüchtern.

G. B.

Related articles:

Germany

New Railway Line Gelnhausen–Fulda: 28 km of the Route will run in Tunnels

After weighing the advantages and disadvantages, German Railways (DB) announced a preference for a new line between Gelnhausen and the Fulda–Würzburg high-speed line at the Dialogforum...

more

Last sleeper laid in the Gotthard Base Tunnel

Switzerland. On October 31, 2014 the last rails were laid in the Gotthard Base Tunnel. At a distance of around 54 m from the south portal, the contractor cast the “golden sleeper”. A big moment for...

more
02/2010

Austria Koralm Railway: Inviting Submissions for the longest Tunnelling Contract Section

The Koralm Railway is the extension of the trans-European corridor VI and part of the axis from Danzig via Warsaw and Vienna to Triest, Venice and Bologna, in other words the link between the Baltic...

more
05/2011 Austria

Koralm Tunnel: Work starts on main Section

The Koralm Tunnel represents the core of the new 130 km long Koralmbahn, being set up between Graz and Klagenfurt, a twin-track high-speed line designed for speeds of up to 200 km/h estimated to cost...

more
05/2018 Czech Republic

Railway Tunnel between Rokycany and Pilsen

A convertible Herrenknecht multi-mode tunnel boring machine (Ø 9,890?mm) was used to modernize the Czech railway line between Rokycany and Pilsen. The machine excavated two tunnels, each about 4?km...