Germany

TBM in the Filder Tunnel has completed the first Shield Drive

The tunnel boring machine (TBM) driving the Filder Tunnel as part of the Stuttgart 21 infrastructure project has completed its first drive in the middle of November 2015. The Filder Tunnel (PfA 1.2) has a length of 9.5 km and links the main station of Stuttgart in the valley to the Filder Plain, which is about 155 m higher. Construction is executed by the ATCOST 21 consortium under the technical lead of Porr Bau GmbH.

The Herrenknecht machine called Suse is currently in the east bore, in which the track from Ulm to Stuttgart will later run, at chainage 4080 m. To reach this point in the Stuttgart suburb of Hoffeld, it has installed a lining of 1967 segment rings each consisting of six large precast concrete segments and one keystone.

The machine including cutting wheel will now be dismantled in the tunnel. The shield skin will remain in the tunnel and the backup will be pulled out backwards. In the construction pit at the Filder portal, the TBM will be prepared for the coming excavation of the west bore, which according to information from German Railways DB should start in early 2016.

Related articles:

01/2019 Germany ¤ Deutschland

Filder Tunnel: Unusual TBM Turning Manoeuvre

Video clip of the 180 ° turn (with German commentary)

Client DB Projekt Stuttgart–Ulm GmbH is continuing the construction of the Filder Tunnel as part of the Stuttgart 21 project. With the installation of the first segment rings, tunnelling and thus the...

more
06/2017 Germany

Breakthrough in Filder Tunnel

The 9.5 km long Filder Tunnel connects Stuttgart Central Station, lying in a valley basin, with the Filder plateau located some 155 m higher. The four sections of its two tunnel tubes are being driven...

more
06/2014 Germany

Stuttgart 21: Construction of the Filder Tunnel has commenced

In July a new phase has begun in the construction of Stuttgart‘s underground railway station as political and business representatives celebrated commencement of construction of the Filder Tunnel....

more
04/2017 Germany

Boßler Tunnel: TBM commenced Building the second Tunnel Tube

Käthchen, the tunnel boring machine (TBM), which the DB Projekt Stuttgart–Ulm GmbH is using to drive the Boßler Tunnel on the new Wendlingen–Ulm rail route, embarked on its second shield passage...

more
06/2016 Germany

One Third of the Tunnels of Stuttgart 21 driven

The DB Projekt Stuttgart–Ulm GmbH passed the 20 km mark for tunnelling on the Stuttgart 21 project at the end of September 2016, meaning that more than a third of the tunnels for the reorganisation...

more