Germany

U5 Europaviertel, Frankfurt: Tunnel Excavation Completed

The extension of the U5 urban railway line in Frankfurt a.M. will connect the Europaviertel to the city‘s underground network. The ARGE U5 Europaviertel, consisting of the Porr teams of civil engineering, tunnelling and the subsidiary Stump-Franki Spezialtiefbau, is working shoulder to shoulder to construct the 1160 m long section. An important project step has now been achieved: at the end of March 2022, the mining excavation was safely completed – the existing wall has been exposed in both tunnel tubes.

U5 Europaviertel project: View of the launch pit in the Europa-Allee
Credit/Quelle: Porr

U5 Europaviertel project: View of the launch pit in the Europa-Allee
Credit/Quelle: Porr

The difficult conditions of inner-city tunnelling posed great challenges for all those involved. For the first time, a tunnel was constructed in Frankfurt a. M. using mechanised tunnelling. In September 2019, the 580-tonne tunnel boring machine (TBM) had begun to work its way through the soil in the south tube. At the end of May 2021, the TBM reached its final position in the north tube. As the TBM moved forward, the tunnel construction team had simultaneously installed a total of 8358 segments for the supporting concrete tubes. The last metres to the existing wall at the underground tunnel under the “Platz der Republik” were mastered by excavation.

Tunnel Work Under Overpressure

The groundwater is about 3–5 m below ground level, so that the tunnel is completely in groundwater in the area of the connection. So that the work could be carried out, the mining excavation was carried out using the overpressure method and under the protection of an ice body. In the sensitive, densely built-up inner city location, it was important not to endanger the existing buildings and above-ground traffic during the tunnel construction work. In the course of the overpressure procedure, all personnel and work equipment had to be brought in and out in a complex manner, which made the work all the more complex. The work was carried out in 3 shifts of 6 hours each. In addition, 1.5 hours were needed to lock and unlock in the pressure chamber. At the end of March 2022, the mining excavation under the Frankfurt skyline was safely completed. The existing wall behind which the U5 currently turns is exposed in both the north and south tubes. After completion of the excavation, the next step will be the construction of the inner tunnel shell.

Special Civil Engineering Work During Ongoing Tunnel Excavation

Parallel to the tunnelling work, the special civil engineering work progressed above ground on the construction site in Europa-Allee. A total of 18 wells were drilled by Stump-Franki Spezialtiefbau in late summer 2021 for dewatering to relieve and monitor groundwater levels using a rotary drilling rig. In order to relieve the groundwater within the excavation pit in all areas, an additional 92 relief lances were constructed.

x

Related articles:

Issue 02/2018 Germany

Extension of the Urban Railway Line U5 in Frankfurt/Main

With the extension of the urban railway line U5 past the main station to the west, Frankfurt’s Europaviertel quarter will gain a high-capacity link to the public transport network of the city. The...

more
Issue 02/2022 Canada

Tunnelling for Canada’s Largest Outfall Completed

The completed wastewater outfall will connect to the 50 in-lake risers to enable efficient dispersion of treated effluent over a wide area of the lake, making it the largest outfall in the country....

more
Issue 04/2016 Switzerland

Galgenbuck Tunnel: Excavation completed

The connection Schaffhausen south of the Swiss autobahn A4 is to be rearranged, the road network of the city Schaffhausen will be connected to the Klettgau and the municipality of Neuhausen at the...

more
Issue 08/2016 Germany

Construction start for S-Bahn Tunnel Gateway Gardens, Frankfurt

On the approx. 35 hectare site of the former American military housing estate Gateway Gardens in close proximity to Frankfurt Airport, a new city quarter is being developed with office and conference...

more
Issue 02/2022 Germany

Ground Freezing Measures for the Extension of the U in Frankfurt am Main

Ground freezing is a flexible procedure that is mainly used for complex measures and for construction works involving existing structures. Here, the ground is solidified and made impermeable to water...

more