USA

Norris Cut Project: Tunneling at Florida’s Coast

In February 2016 construction company Bessac completed work on the Norris Cut protection tunnel in extremely difficult geology in South Florida. Norris Cut is a shallow inlet between Fisher Island and Virginia Key, just south of the Main Channel to the Port of Miami.  In just ten months and using a customized machine designed especially for the mission, a “Herrenknecht Combined Shield” (HCS, diameter 3.13 m), 1613 m were tunnelled adhering to the highest safety standards. A new sewer line was installed in the finished tunnel – after half a century in use the old pipe was simply worn out.

The Miami-Dade Water and Sewer Department had awarded Nicholson Construction the 72 million dollar design-build contract in January of 2014. Nicholson served as the General Contractor for the project, working closely with sister company and tunnel construction manager Bessac and tunnel design firm, Arup.

Safeguard Measures against Flooding

The ground conditions and project circumstances of the mission at Norris Cut were anything but standard. Not only did the karstified, permeable geology pose the risk of flooding the machine. The complex Fort Thompson Formation to be tunnelled through is also full of sand-filled cavities. The tunnel face was therefore prone to instability.

For this reason the construction of the protection tunnel for a new sewer line between Virginia Key and Fisher Island required the flexibility and special safety features of the HCS machine. Available in slurry mode as well as in EPB mode depending on the requirements, the HCS offered the necessary adaptability to changeable ground conditions.

Additionally, the front area of the machine had to be accessible at all times during the excavation to allow for tool changes, for instance. For maximum safety a bulkhead with a dive pit was developed especially for the project. Thanks to the bulkhead between the front two machine parts and the overpressure thus enabled, muck and water cannot penetrate into the machine at the tunnel face. Should high water pressures nevertheless lead to flooding, the dive pit allows safe locking into the flooded area.

In the end the safety reserves were not needed. Neither the sophisticated lock system nor the EPB mode were used. The ground was highly permeable as expected, however the proper design of the cutterhead and the appropriate disc cutters necessitated only one maintenance stop, performed under compressed air after an innovative ground treatment from the TBM.

Construction started in Pipe Jacking Mode

The TBM “Dorsey” began the drive near the treatment plant on Virginia Key in April 2015. Right from the start the project was characterized by its special requirements: to save space, with a diameter of 12 m the launch shaft was rather small. At the beginning there was no room for the HSC machine‘s back-ups and they were only able to be used one by one after 70 m of tunnelling. For the first section the TBM was therefore pushed forward in pipe jacking mode using a jacking frame adapter developed by the customer, the rest of the tunnel was then lined with concrete segments.

At a depth of up to 21 m below sea level, the TBM dug its way forward in the months that followed. After 227 working days came the breakthrough on Fisher Island on February 16, 2016. By the end of the year the new 60“ discharge pipeline is due to be installed in the finished protection tunnel and put into operation.  “The project has set standards for work in Florida‘s underground and showed solutions for deep sewer lines in the porous Fort Thompson Formation,” said Bernard Theron, President of Bessac.

Related articles:

Issue 2016-07 USA

Norris Cut Projekt: Tunneling at Florida’s Coast

In February 2016 construction company Bessac completed work on the Norris Cut protection tunnel in extremely difficult geology in South Florida. Norris Cut is a shallow inlet between Fisher Island and...

more
Issue 2018-05 Czech Republic

Railway Tunnel between Rokycany and Pilsen

A convertible Herrenknecht multi-mode tunnel boring machine (Ø 9,890?mm) was used to modernize the Czech railway line between Rokycany and Pilsen. The machine excavated two tunnels, each about 4?km...

more
Issue 2019-03

Job Offer

STUVA seeks Engineer for Fire Protection and Safety (m/f/d) The STUVA is looking for an engineer of any sex to expand its team in the long term on the fire protection and safety sector. The new...

more
Issue 2014-02 USA

Port of Miami Tunnel is set to be opened in May

As link to the Interstate 195 and 95 freeways the 1.2 km long Port of Miami Tunnel with two bores, each with two lanes, underpasses the channel for the world’s biggest cruise ship harbour on the...

more
Issue 2017-08 Switzerland

Breakthrough at the Bözberg Tunnel

An important milestone for the 4 m corridor: On 29 November 2017, the tunnel boring machine broke through the last few metres of the Bözberg in Effingen. Due to the presence of unstable rock at the...

more