Brenner Base Tunnel

Isarco River Underpass Construction Site: Ground Freezing for the First Main Tunnel

After the first connecting tunnel was successfully excavated under the Isarco river, the next freezing phase was started in March 2021 in order to subsequently drive the first of the two main tunnels under the river.

In the municipality of Fortezza works on the Isarco River Underpass construction site, which is the southernmost construction lot of the Brenner Base Tunnel, are proceeding at full speed. The complex freezing procedure already produced successful results in autumn 2020. The following step was to proceed with the excavation works for the first connecting tunnel below the Isarco river. In mid-March 2021, the ground under South Tyrol's second longest river was again artificially frozen in order to start the excavation work for the first main tunnel under the Isarco river.

 

Freezing Procedure for the Isarco River Underpass

As the Isarco river is located on the new tunnel route, two shafts have been excavated at the Isarco River Underpass construction site, on each side of the river. The four shafts are about 25 m deep. In order to excavate the tunnels below the river, the groundwater is frozen starting from the shafts by circulating a refrigerant fluid inside the soil through special heat exchangers. As a first step, liquid nitrogen is injected to this effect in a closed pipe circuit below the river bed. The refrigerant substance has a temperature of -196 °C and is eventually dispersed into the atmosphere as a gas. The following step is about maintaining the temperature between -30 and -35 °C by using saline brine, so that the ground stays frozen, allowing the excavation works for the underpass to proceed.

This highly complex procedure was deemed necessary to avoid relocating the Isarco river from its original river bed. The significant advantage of this freezing procedure is the lack of environmental impact. This ensures that the diversity of the river’s flora and fish fauna is preserved.

 

Construction Progress at the Brenner Base Tunnel

In March 2021, four main construction lots were under construction:

Mules 2–3 and, Isarco undercrossing (in Italy)

Tulfes–Pfons and Sill Gorget (in Austria)

 

To date, 138 km of the total 230 km planned in the project have been built. Of these, 47 km are main tunnels, 51 km are exploratory tunnels and 40 km are other tunnel structures, such as access tunnels or logistics tunnels.

x

Related articles:

Issue 2021-02 Brenner Base Tunnel | Brenner Basistunnel

Isarco River Underpass Construction Site: Ground Freezing for the First Main Tunnel

In the municipality of Fortezza works on the Isarco River Underpass construction site, which is the southernmost construction lot of the Brenner Base Tunnel, are proceeding at full speed. The complex...

more
Issue 2020-06 Italy

Brenner Base Tunnel: First Breakthrough at the Isarco River Underpass

Starting from one of the four shafts built on the Isarco River Underpass construction site, the underlying aquifer and alluvial deposits below the riverbed were frozen by injecting liquid nitrogen...

more
Issue 2014-08 Italy?/?Brenner Base Tunnel

Contracts signed for the Isarco River Underpass

At the end of a public tender procedure published at the European level, BBT SE awarded the contract for executive planning and works for the Isarco River Underpass to the temporary consortium made up...

more
Issue 2015-02 Brenner Base Tunnel

BBT: Start of Works on the main Tunnel

The work on the Brenner Base Tunnel, the 64 km long heart of the new Brenner rail line between Munich and Verona, is progressing apace. On March 19, 2015, work began on the main tunnel in Austria....

more
Issue 2021-03 Italy

Advance Record at the Brenner Base Tunnel

On the Italian construction lot “Mauls 2–3” of the Brenner Base Tunnel, three Herrenknecht tunnel boring machines (TBMs) are boring from south to north. They are excavating the two main tubes as...

more