Switzerland

Ceneri Base Tunnel: Drive towards the South completed

On March 30, 2015, the tunnellers broke through the final few metres of the Ceneri Base Tunnel’s east bore between Sigirino and Vezia. Some two weeks after the first breakthrough in the west bore on March 17, which took place 13 months earlier than scheduled, this signifies that both southbound single-track tunnels for the tunnel have been excavated. Some 400 m away from the south portal in Vezia more than 600 persons involved in the project, watched on as the precise breakthrough for the west bore towards the south took place: the deviation was extremely minimal – amounting to 2 cm horizontally and 1 cm vertically. Currently the northbound drives are forging ahead. In the west bore around 1500 m must be excavated, with some 2000 m still to be accomplished in the east bore. The  main breakthrough is scheduled for early 2016. According to Renzo Simoni, the CEO of the AlpTransit Gotthard AG, the scheduled deadline for opening the tunnel remains December 2019.

Related articles:

Issue 2016-01 Switzerland

Breakthroughs in both Ceneri Base Tunnel Tubes

The main breakthrough took place in the western bore of the Ceneri Base Tunnel on January 21, 2016. Shortly after this final round of blasting the tunnellers were able to exchange handshakes. The...

more
Issue 2010-04 Switzerland

Gotthard Axis – Situation in March 2010

The CEO of the AlpTransit Gotthard AG Renzo Simoni reported on progress achieved in building Switzerland’s biggest construction project during the premiere of the 2009 AlpTransit annual film on March...

more
Issue 2010-07 Switzerland

Gotthard Base Tunnel: TBM restarts in Faido west tunnel

On 4 March 2010 excavation had to be stopped in the west tunnel of the Gotthard Base Tunnel some 9 km from the Faido multifunction station due to a rock inrush, and exploratory bores had to be...

more
Issue 2017-06 Switzerland

Ceneri Base Tunnel – Installation of Railway Equipment has begun

At the north portal of the Ceneri Base Tunnel, installation of railway equipment in the east bore started in summer 2017. The 15.4 km long base tunnel between Camorino and Vezia will be equipped in...

more
Switzerland

Ceneri Base Tunnel: Operational opening delayed to December 2020

The legal dispute concerning the award of the railway systems for the Ceneri Base Tunnel has consequences. An intensive review by the constructor, AlpTransit Gotthard Ltd (ATG), has concluded in...

more