Gotthard Base Tunnel

Pressure Exchange System: Cooling Technology for working Underground

The opening of the Gotthard Base Tunnel on June 1, 2016 is an occasion for Siemag Tecberg to reflect on a project that involved unique challenges. The shaft hoisting system in the Sedrun part-section was built by Siemag Tecberg, who also operated the system during the construction phase. The hoisting plant was a critical logistical resource providing the means of access for construction supplies and of removal for the excavated material for the 8.5 km central section, which was driven by drill+blast.

The cooling for the underground worksite was provided by a further Siemag Tecberg technology, in the form of the “Pressure Exchange System” (P.E.S.). The P.E.S. has the function for efficiently supplying the underground cooling network with cold water from the surface.

Primarily the P.E.S. was developed for mining applications; this technology has a strong reputation in the sector, which is reflected by numerous references. As the example of the Gotthard Base Tunnel demonstrates, the technology can be applied to other sectors such as tunnelling.

The P.E.S. is a central element in the Sedrun mid-section cooling facility. It forms the interface between the high-pressure water circuit and the low-pressure water circuit. The high-pressure circuit connects the main cooling facility on the surface with the Pressure Exchange System located in the tunnel. From there, the low-pressure circuit connects the P.E.S. with the underground coolers, delivering cold water around the system.

The use of a P.E.S. in this type of application has several technical advantages, particularly to the low temperature loss achievable, which benefits whole system efficiency.

A detailed article on the P.E.S. technology will be presented in detail in tunnel at a future date.

x

Related articles:

Issue 04/2010

Gotthard Base Tunnel: Stage reached by Work

The roughwork execution and the concreting operations for the inner lining also progressed parallel to the drive at all construction sites. At the end of 2009, 85 from 176 cross-passages had been...

more
Issue 03/2011 Switzerland

Gotthard Base Tunnel: Drive concluded

On March 23, 2011 at 20 past 12 noon the tunnel boring machine broke through from the Faido western bore into the Sedrun part-section (title page); in this connection the deviations from the intended...

more
Issue 06/2011 Collecting Underground Water

Specially developed Membrane in Gotthard Base Tunnel

A specially devised dimpled sheeting was installed in the Gotthard Base Tunnel to collect seepage and crack water over large areas. One of the most important prerequisites for the operational safety...

more
Issue 03/2016 Switzerland

Control System provides Safeness in the Gotthard Base Tunnel

The Gotthard Base Tunnel opens on June 1, 2016. Generally nobody is allowed to stay in the tunnel anymore. In order to prevent accidents when necessary maintenance work is performed and sections are...

more
Issue 04/2010 Dachzeilentext Englisch

Gotthard Base Tunnel: Surveying by the Client

Untertiteltext Englisch

Requirements on Surveying At the very most 25 cm crosswise and along the tunnel and 12.5 cm in elevation are tolerated as deviations for the Gotthard breakthroughs. In order to remain inside these...

more