Austria

BBT SE Awarded Contract for New “Hochstegen” Construction Lot

The contract for the construction lot H52 “Hochstegen” in the area of Steinach am Brenner was awarded to the company Swietelsky Tunnelbau GmbH & Co KG. The contract for the construction work on this complex lot was awarded on 15 December 2021. The construction period has a duration of 23 months; the tender amount is around 102 million euros. Work is scheduled to start at the beginning of 2022.


The Europe-wide tender was carried out according to the best bidder principle. Swietelsky was already responsible for the preliminary lot “Wolf II” (construction period: 2013–2017) of the Brenner Base Tunnel.

The new construction lot H52 “Hochstegen” is a section of the former construction lot H51 “Pfons–Brenner”. This previous project section was divided into several construction lots for the purpose of ensuring that the work can be continued as quickly and efficiently as possible.

Overview of the new construction lot H52 “Hochstegen”
Credit/Quelle: BBT SE

Overview of the new construction lot H52 “Hochstegen”
Credit/Quelle: BBT SE

 

Hochstegen – a Challenging Geological Zone

The area of the new construction lot Hochstegen is located in a geological fault zone with extremely complex geology. Over a length of approximately 500 m, water-bearing, carbonate rock layers predominate. This makes tunnelling in this zone particularly challenging.

A total of about 2.6 km of main tunnel in the direction of Brenner, 0.6 km of connecting tunnels, five cross-passages and 1.2 km of exploratory tunnel in the southern direction have to be excavated. In addition, there is a 2.5 km long remaining excavation of the crossover at the Wolf South junction. The centrepiece of the project, however, is the excavation of the exploratory tunnel to the south through the so-called “Hochstegenzone”. The excavation in this area will be protected by advance sealing and stabilisation injections.

 

Overall Progress of the Brenner Base Tunnel Project

At the beginning of 2022, two new construction sections will start on Austrian project territory with the two lots H41 “Sillschlucht–Pfons” (contract awarded on 17 November 2021) and H52 “Hochstegen”.

Of a total of 230 tunnel kilometres of the Brenner Base Tunnel, 148 km have already been excavated, of which 53 km are railway tunnels, 54 km are exploratory tunnels and 41 km are other structures.

www.bbt-se.com

x

Related articles:

Issue 01/2022 Austria

Brenner Base Tunnel: Tender Launched for Pfons–Brenner Construction Lot

If the tendering process goes according to plan, the Pfons–Brenner construction lot is expected to be awarded within 2022. The construction period for the services to be carried out is estimated at...

more

Brenner Base Tunnel: Contract Awarded for Lot “H53 Pfons–Brenner”

A few days after the end of tunnelling for the TBM Virginia in the main tunnel east, BBT SE awarded the contract for the construction lot “H53 Pfons-Brenner” in early April 2023. A consortium...

more
Austria

Brenner Base Tunnel: Largest Contract Section awarded on Austrian Side of Project

With the awarding of the largest contract section on the Austrian side of the project, Pfons–Brenner, a significant step has been taken in accomplishing the longest underground rail link, the Brenner...

more
Issue 03/2018 Austria

Brenner Base Tunnel: Largest Contract Section awarded on Austrian Side of Project

With the awarding of the largest contract section on the Austrian side of the project, Pfons–Brenner, a significant step has been taken in accomplishing the longest underground rail link, the Brenner...

more
Austria

Brenner Base Tunnel: BBT SE Terminates Construction Contract with ARGE H51 Pfons–Brenner

The BBT SE’s Perspective: “The final refusal to carry out the contractually agreed works and the subsequent loss of trust has unfortunately forced us to dissolve the contract with ARGE H51. Even...

more