Full Renewal of the Wihalden Tunnel‘s Coating

The Wihalden Road Tunnel in the Swiss canton of St. Gallen is a key part of the regional transport infrastructure. In October 2025, the existing tunnel coating was completely renewed as part of a compact night-time repair project.

MC-DUR 2496 CTP – Application using the airless spraying method
Credit/Quelle: MC-Bauchemie

MC-DUR 2496 CTP – Application using the airless spraying method
Credit/Quelle: MC-Bauchemie
This project, commissioned by the St. Gallen Civil Engineering Office, involved the refurbishment of approximately 3500 m² of tunnel wall surface. The aim was to replace the existing coating to ensure long-term surface protection and good visibility within the tunnel.

Night-Time Refurbishment Within a Tight Timeframe

The coating work was carried out within a tight timeframe of just one week, with work from 7.30 pm to 5.00 am each night. During these hours, the tunnel was completely closed to general road traffic. The work was carried out by the experienced specialist contractor Hydrojet AG, who applied the MC-DUR 2496 CTP tunnel coating from MC-Bauchemie.

In addition to the light-coloured coating applied to the standard tunnel wall surfaces, safety-critical areas were highlighted in colour: emergency exits were coated in RAL colour 6029 (mint green), whilst the SOS niches were finished in RAL colour 2004 (pure orange).

Safe Implementation in Autumnal Weather Conditions

The work took place in autumnal conditions – with low night-time temperatures of between 3 and 7 °C and high humidity. These conditions present a considerable challenge for coating work in tunnels, as they can affect both the workability and the curing of the materials. Added to this was the significant time pressure caused by the narrow night-time working window: Every step of the process had to be carried out with precision to ensure the construction schedule could be maintained without delays.

View inside the fully coated Wihalden Tunnel in the Swiss canton of St. Gallen
Credit/Quelle: MC-Bauchemie

View inside the fully coated Wihalden Tunnel in the Swiss canton of St. Gallen
Credit/Quelle: MC-Bauchemie
The St. Gallen Civil Engineering Office had already defined clear system specifications in the tender. Based on very positive experiences from previous projects – particularly under comparable climatic conditions – the MC-DUR 2496 CTP coating was selected. The project manager in charge was familiar with the product from previous projects and assessed it as ideally suited to the expected weather conditions.

The coating was applied in two layers using an airless spraying method. According to the manufacturer, this tried-and-tested material is characterised by reliable application even at low temperatures and high humidity, as well as by a robust, uniform surface finish. The speed of application and curing were decisive advantages under the given conditions, and the refurbishment of the Wihalden Tunnel with new uniform and durable coating surface was thus completed within the specified timeframe.

x

Related articles:

Issue 02/2019 Heco

Screw Anchors fix Fire Protection Boards in the Pians-Quadratsch Tunnel

For the refurbishment of the 1545 m long Pians-Quadratsch tunnel system on the Arlberg Schnellstraße S16 in Austria, the fire protection boards were fixed using Multi-Monti screw anchors from Heco....

more
Austria

Screw Anchors fix Fire Protection Boards in the Pians-Quadratsch Tunnel

For the refurbishment of the 1545 m long Pians-Quadratsch tunnel system on the Arlberg Schnellstraße S16 in Austria, the fire protection boards were fixed using Multi-Monti screw anchors from Heco....

more
Tunnel Refurbishment

First Tunnel Refurbishment with Cathodic Corrosion Protection in Germany

After the Hamburg Elbe Tunnel dating from 1912, the two-tube 640 m long Rendsburg Canal Tunnel, which opened in 1961, was the second underwater tunnel built in Germany for road traffic. Now it is the...

more
Issue 05/2022

Adaptation Lighting for Road Tunnels

Planning a road tunnel represents a special case from the standpoint of light calculation software and the planning of lighting design. Although lighting equipment is usually planned for night-time...

more
Issue 06/2025 MC-Bauchemie

High-Performance Wall Coating for the Silvertown Tunnel in London

On 7 April 2025, London celebrated a major milestone in urban infrastructure with the official opening of the Silvertown Tunnel. The 1.4-km twin-bore tunnel, which has been constructed at a cost of...

more