Advance Record at the Brenner Base Tunnel

The miners in the Brenner Base Tunnel are pushing ahead rapidly with the major rail project. On March 31, 2021, they achieved a new record while excavating the main tubes in South Tyrol: 860 m of tunnel bored and lined in one month.

On the Italian construction lot “Mauls 2–3” of the Brenner Base Tunnel, three Herrenknecht tunnel boring machines (TBMs) are boring from south to north. They are excavating the two main tubes as well as an exploratory and later service tunnel 12 m below. In March 2021, a new record was set by one of these three machines: the Double Shield TBM (Ø 10.65 m) named “Virginia” covered 860 m in one month. The contracting joint venture BTC S.c.a.r.l. (Astaldi S.p.A., Ghella S.p.A., P.A.C. S.p.A. and Cogeis S.p.A.) thus achieved a peak advance rate at the Mauls jobsite. For March 2021, the Brenner Base Tunnel project owner, Austrian-Italian BBT SE, announced an average daily advance rate of 27.7 m for “Virginia”. The daily best performance was 36.75 m.

By early April 2021, the two machines in the Brenner main tunnels had already covered over 50% of the total distance toward their lot boundary. As the TBM bores, the excavated tunnel is concurrently lined with concrete segments.

At a total length of 64 km, the Brenner Base Tunnel being built under the direction of Austrian-Italian BBT SE will be the longest underground rail link in the world. It crosses beneath the Alps between Innsbruck in Austria and Franzensfeste (Fortezza) in South Tyrol/Italy as a particularly efficient flat trajectory, that is, with very low gradients.

x

Related articles:

Issue 07/2011 Austria/Italy

Brenner Base Tunnel: Main Phase started

Phase III, the main construction phase of the Brenner Base Tunnel (BBT), currently the European Union’s /EU’s) most important transport infrastructural project, was started on April 18, 2011 in...

more
Austria

Symbolic Groundbreaking Ceremony at the North Portal of the Brenner Base Tunnel

The western main tunnel tube heading south was begun. Prior to this, a blessing ceremony was held at the site where the future north portal of the Brenner Base Tunnel will be built. Starting from the...

more
Issue 03/2015

The Core of the European North-South Rail Link

The starting shot for driving the first bore of the Brenner Base Tunnel was fired on March 19, 2015 in the Innsbruck Ahrental Valley. EU transport commissioner Violeta Bulc took over the patronage of...

more
Issue 02/2021 Austria

Brenner Base Tunnel Project Provides Data for Flooding Forecast Models

On World Water Day 2021, which takes place every year on 22 March, the Brenner Base Tunnel Society (BBT SE) drew attention to a positive effect of the construction works. The insights collected...

more
Austria

Brenner Base Tunnel: Largest Contract Section awarded on Austrian Side of Project

With the awarding of the largest contract section on the Austrian side of the project, Pfons–Brenner, a significant step has been taken in accomplishing the longest underground rail link, the Brenner...

more