Bids for the largest Construction Lot of the Brenner Base Tunnel

April 18th 2017 was the bid presentation deadline for the largest construction lot for the Brenner Base Tunnel, Pfons–Brenner. The construction lot includes the excavation of the main tunnels
between Pfons and Brenner, about 9 km of exploratory tunnel and the emergency stop and the cross-over at St. Jodok. In total, about 50 km of tunnel will be driven.

Five Bids tendered

This lot was tendered at a European level according to the MEAT principle and on the basis of Austrian tender law (BVergG 2006, as amended in 2016). Five bids were tendered, from the following consortia:

Impresa Pizzarotti & C. S.P.A., Implenia Österreich GmbH,
Metrostav a.s., BeMo Tunnelling GmbH

Strabag AG, Salini Impregilo

Acciona Construcción, S.A., Impresa Cooperativa Muratori & Cementisti – C.M.C. di Ravenna Società Cooperativa

Astaldi S.p.A., Ghella S.p.A., Oberosler Cav. Pietro S.r.l., P.A.C. S.p.A.

Porr Bau GmbH, G. Hinteregger & Söhne Baugesellschaft m.b.H., Società Italiana per Condotte d’Acqua S.p.A., Itinera S.p.A.

A Fourth of the Excavation Works is already done

After the  evaluation of the qualitative criteria the price bids will be opened in a public hearing. The Austrian CEO of BBT SE, Prof. Konrad Bergmeister, considers this tender procedure as a further milestone for the construction of the tunnel, since over 80 % of the works have now been tendered. Six years before, on April 18th 2011, the construction phase was launched. Until April 2017, 61 km of tunnel had been driven – about a fourth of the total volume of excavations.

x

Related articles:

Issue 01/2022 Austria

Brenner Base Tunnel: Tender Launched for Pfons–Brenner Construction Lot

If the tendering process goes according to plan, the Pfons–Brenner construction lot is expected to be awarded within 2022. The construction period for the services to be carried out is estimated at...

more

Brenner Base Tunnel: Contract Awarded for Lot “H53 Pfons–Brenner”

A few days after the end of tunnelling for the TBM Virginia in the main tunnel east, BBT SE awarded the contract for the construction lot “H53 Pfons-Brenner” in early April 2023. A consortium...

more
Issue 02/2023 Austria/Italy

Brenner Base Tunnel: TBM Virginia Has Reached the Brenner

After 4 years, the first tunnel boring machine (TBM) of a main tunnel in the Brenner Base Tunnel successfully completed driving on 30 March 2023. TBM Virginia covered around 14 km on its journey,...

more
Austria + Italy

Construction Progress at the Brenner Base Tunnel

Start of Tunnelling Works at South Exploratory Tunnel On 29 March 2019 tunnelling work for the fourth drilling of Lot H51 Pfons–Brenner began on the south exploratory tunnel, marked by a drilling...

more
Issue 03/2019 Austria + Italy

Construction Progress at the Brenner Base Tunnel

Start of Tunnelling Works at South Exploratory Tunnel On 29 March 2019 tunnelling work for the fourth drilling of Lot H51 Pfons–Brenner began on the south exploratory tunnel, marked by a drilling...

more