Custom Timber Formwork for the Feuerbach Tunnel

The Tunnel Feuerbach project between Stuttgart‘s main railway station and the Feuerbach station, which was commissioned at a cost of around 187 million euros, has been completed. The breakthrough of the 3 km long tunnel in June 2020 was followed by the complex and innovatively designed inner lining of the tunnels and the branching structure near Feuerbach station. Complex because the tunnels taper conically before reaching the station and the formwork had to be continuously adapted to the changing geometry. And innovative because the tunnel runs through large areas of anhydrite rock, which swells on contact with water and builds up enormous pressure. As a preventive measure, the tunnel lining and reinforcement were therefore strengthened accordingly. Previously, this tunnel through anhydrite was considered too much of a technical challenge; the massive formwork as well as reinforcement levels and the placement of concrete with a necessary thickness of up to 1.2 m were not considered feasible.

However, the three companies Baresel Tunnelbau GmbH, Kunz Untertagebau GmbH and Bertschinger Bau GmbH, organised in a consortium, completed the Feuerbach Tunnel in spring 2022. All customised formwork, including assembly and supervision, was provided by the company Huber & Sohn from Bachmehring (Eiselfing) in Bavaria, Germany. The project and site managers of Baresel Tunnelbau, Johann Bachsleiter and Lars Preiß, as well as the site managers for the inner shell concrete at the August Reiners company had agreed on this.

The Huber & Sohn formwork team, headed by Günther Pilger, constructed all the...

Related articles:

Issue 03/2022

Special Formwork for Feuerbach Tunnel

For the supply of all special formwork (such as formwork for the widening, connecting structures, cross-passages and the access of the Prague intermediate access), the JV Tunnel Feuerbach (Baresel...

more
Issue 06/2009 Formwork Technology

Stable Tunnel Formwork Carriage with flexible Design

A large number of infrastructural schemes are being executed in the region for the 2014 Winter Olympics to be held in the Black Sea resort of Sochi. These include a roughly 13??km long bypass for the...

more
Issue 01/2023 Formwork Technology

Fully Hydraulic Crawler Driven Formwork Carriage for Varying Tunnel Cross-Sections

Since May 2020, tunnel construction work has been underway to the north and south of the Danube for the future accesses and exits of the suspension bridge. Five different tunnel cross-sections, the...

more
Issue 06/2011 Gotthard Base Tunnel

Fully-hydraulic Forming for complex Tunnel Cross-Section

In the Gotthard Base Tunnel’s Erstfeld section a fully hydraulic and flexibly adjustable tunnel forming carriage served to execute the inner shell for 2 branching structures, which tapered greatly in...

more
Issue 03/2013 Germany

Bleßberg Tunnel; Shuttering Panels made of solid Plastic secures better Result with lower Costs

Admittedly replacing shuttering panels takes time and money and in tunnelling this procedure is always especially complicated and expensive. Thanks to the robust alkus solid plastic panel, the Huber &...

more