Germany

Boßler Tunnel: TBM commenced building the second Tunnel Tube

Käthchen, the tunnel boring machine (TBM), which the DB Projekt Stuttgart–Ulm GmbH is using to drive the Boßler Tunnel on the new Wendlingen–Ulm rail route, embarked on its second shield passage on April 18, 2017. The 11.39 m diameter cutting wheel began tackling the roughly 8800 m long west bore from the Aichelberg portal. In similar vein to the parallel running east tube, which was accomplished in November 2016, the 110 m long and 2480 t heavy tunnelling machine will install some 4400 tunnel rings comprising roughly 30 800 precast concrete segments. “Together with the contractor we had the ambitious aim of sending Kätchen on her second trip immediately after the Easter holidays”, commented Jörg Müller, DB project manager for the Albaufstieg contract section. “I have to thank all those involved for attaining this milestone”, Müller added. Planning foresees the TBM reaching the light of day at the other end of the tunnel above the Filstal Valley near Mühlhausen im Täle in autumn 2018.

Related articles:

Issue 2017-04 Germany

Boßler Tunnel: TBM commenced Building the second Tunnel Tube

Käthchen, the tunnel boring machine (TBM), which the DB Projekt Stuttgart–Ulm GmbH is using to drive the Boßler Tunnel on the new Wendlingen–Ulm rail route, embarked on its second shield passage...

more
Issue 2015-04 Germany

Boßler Tunnel: 1000 m excavated, mechanized Drive scheduled to be extended

The DB Projekt Stuttgart-Ulm GmbH is forging ahead with the construction of the Boßler Tunnel as planned. It is the longest tunnel on the new Wendlingen-Ulm rail route with a length of 8806 m. The...

more
Issue 2015-08 Germany

First Tunnel Boring Machine approved for Rastatt Tunnel

The first of two tunnel boring machines (TBMs) for the Rastatt Tunnel by manufacturer Herrenknecht was approved by the customer, the Tunnel Rastatt JV, on December 8, 2015 at the factory in Schwanau....

more
Issue 2015-03 Germany

TBM at the Boßler Tunnel starts Drive and Ring Construction

The TBM named “Kätchchen” used to drive the Boßler Tunnel began its work in mid-April, 2015. The machine built by Herrenknecht first tackled the eastern bore, which will one day accommodate the...

more
Issue 2010-03 Austria

Breakthrough at Pfänder Tunnel

A second bore for the 6.6 km long Pfänder Tunnel was driven with a tunnelling machine (S-494, Herrenknecht AG) with 11.85 m cutterhead diameter. The support was provided with 25 cm thick and 2 m...

more