The Boßler Tunnel – the longest Tunnel on the new Line Wendlingen–Ulm
The Boßler Tunnel is currently under construction in the planning section 2.2 “Albaufstieg” on the new line from Wendlingen to Ulm as part of the upgrading of the “Main Line for Europe” (central European west-east rail corridor). The single-pass tunnel is bored by a tunnel boring machine (EPB-TBM) and has an excavated diameter of 11.39 m. The lining of the two tunnel bores consists of 45 or 65 cm thick reinforced concrete segments. The length of each bore is 8806 m. In particular the forecast squeezing rock conditions and karst phenomena pose engineering challenges. In the first seven months of tunnelling from April to October 2015, 2959 m were driven and 1457 segment rings were installed.
Overview of the overall Project
The Stuttgart–Ulm rail project is divided into the project sections Stuttgart–Wendlingen (Stuttgart 21) and the new line Wendlingen–Ulm. The project section Stuttgart–Wendlingen is divided into seven planning sections (PFA) and includes the rail junction at Stuttgart, the redesign of Stuttgart main station, the Filder station at the airport, the new line from the airport to Wendlingen and associated access lines. The construction works include altogether 18 bridges, 16 tunnels and culverts. The largest tunnel in this section (PFA 1.2) is the Filder Tunnel with a...