India

Breakthrough in the Himalayas: Second TBM Reaches Its Destination Near Rishikesh

In late June 2025, the last of two Herrenknecht Single Shield TBMs successfully completed its drive for the new railway line between Rishikesh and Karnaprayag in the Indian Himalayas. The first machine had already reached its destination in mid-April. Now both parallel tubes of the more than 20-kilometer-long tunnel system are complete.

Teamwork pioneering in the Himalayas: experts from Larsen & Toubro and Herrenknecht in front of the main portal
Credit/Quelle: Herrenknecht

Teamwork pioneering in the Himalayas: experts from Larsen & Toubro and Herrenknecht in front of the main portal
Credit/Quelle: Herrenknecht
 

Railway Line Rishikesh–Karnaprayag

The young Himalayas were long considered virtually unconquerable for tunnelling. Only a few projects in the region's complex geology have been crowned with success to date. This makes the breakthrough of the second machine in late June even more significant, after the first TBM had already reached its destination in mid-April.

Once completed, the new railway line between Rishikesh and Karnaprayag will reduce the journey time from seven hours to just over two. This represents significant improvements for the region, which serves as an important starting point for Hindu pilgrimages to the sacred Char Dham shrines. Every year, millions of pilgrims take the arduous route along winding roads through deep gorges, which are frequently blocked by landslides and rockfalls in the seismically active zone.

 

Mechanized Tunnelling in the Himalayas

High-tech underground: Single Shield TBMs are the ideal machine type for tunnelling in rock and other stable, non-water-bearing soils
Credit/Quelle: Herrenknecht

High-tech underground: Single Shield TBMs are the ideal machine type for tunnelling in rock and other stable, non-water-bearing soils
Credit/Quelle: Herrenknecht
Assembly of one of the two Single Shield TBMs in front of the portal, on the jobsite directly above the Ganges
Credit/Quelle: Herrenknecht
Assembly of one of the two Single Shield TBMs in front of the portal, on the jobsite directly above the Ganges
Credit/Quelle: Herrenknecht
The project owner, Rail Vikas Nigam Limited (RVNL), awarded the contract for the line's centerpiece – a 10.5-kilometer-long twin-tube tunnel – to civil contractor Larsen & Toubro Limited (L&T).

“Indian miners have extensive experience in conventional tunnelling. For a long time, mechanized tunnelling technology was hence viewed by them with skepticism,” explains Sumit Gaur, Herrenknecht’s project manager on site. This skepticism had historical reasons: until now, machine technology has had too few successes in the Himalayas. This project was to change that. L&T therefore opted for two Single Shield TBMs with a diameter of 9110 mm, designed to meet the challenges of Himalayan geology.

 

Cutterhead with Torque Box Cylinders

The biggest challenge was the predominant rock type: phyllite. L&T Project Leader & Tunnel expert Chris Cooper explains: “Phyllite is soft but stable. It disintegrates with water. Too much pressure and it clumps together and blocks the cutterhead. That doesn't exactly make the drive easy.”

To make matters worse, the young, active rock mass is still moving. This can result in subsidence, causing rock to be deposited on the shield skin of the machine and block its progress. To prevent this, the crew can use so-called torque box cylinders. They were integrated into the cutterhead design. “It's the first time we've had this system on a machine in India,” says Sumit Gaur. These allow infinitely variable horizontal and vertical adjustment of the main drive and can increase the excavation diameter by up to 100 mm if necessary.

 

Geological Pre-Exploration During Advance

In addition to the innovative torque box technology, the TBMs are equipped with the Herrenknecht ISP system. This sends a surface wave along the tunnel wall, which turns into a spatial wave at the tunnel face. The system records the measurement and excavation data obtained during tunnelling in real time and translates it into a geology report. In an anomaly is detected, additional probe drilling is carried out to check the suspected fault zone. This contributes to safety and a smooth drive. “This is a great advantage for our customers and, of course, especially for our colleagues on the machine,” emphasizes Sumit Gaur. Additionally, a convergence measurement system continuously analyzes the distance between the shield and the rock. If the rock is getting too close to the machine, the machine operator is shown a limit signal.

 

Reference Project for Future TBM Tunnelling in the Himalayas

Ready for use: the segments are stored in front of the main portal until they disappear into the tunnel with a multi-service vehicle from Herrenknecht subsidiary TMS to line the inner wall
Credit/Quelle: Herrenknecht

Ready for use: the segments are stored in front of the main portal until they disappear into the tunnel with a multi-service vehicle from Herrenknecht subsidiary TMS to line the inner wall
Credit/Quelle: Herrenknecht
The comprehensive range of equipment installed on the machine paid off. In record time, 23 rings were installed in just 24 hours. Consequently, at peak times one of the machines advanced a good 39 m in a day. “That's impressive, especially in this rock and with this large diameter,” comments Cooper. Fast is also the transport of spare and wear parts. L&T Project Director Rakesh Arora says: “Herrenknecht has its own purpose-built warehouse less than three hours from here in Dehradun and can therefore easily supply new parts when needed. This gives us the flexibility we need.”

Breakthrough of the first of two Herrenknecht Single Shield TBMs in April 2025
Credit/Quelle: Herrenknecht

Breakthrough of the first of two Herrenknecht Single Shield TBMs in April 2025
Credit/Quelle: Herrenknecht
With the successful completion of both tunnel drives, the experts have proven that modern tunnel boring machines can also cope with the extreme conditions of the Himalayas. “Here we've shown we can move faster with the technology used here than with conventional drill & blast,” emphasizes Cooper. The project provides important references for subsequent tunnelling projects in this geologically complex region.

x

Related articles:

Issue 08/2011

Optimising Interfaces for Shield Drives in Sochi

Preparations are in full swing for the 2014 Winter Olympics in Sochi, Russia. Apart from sports facilities and accommodation, an ultra-modern and efficient traffic infrastructure is also being built....

more
Issue 05/2018 Czech Republic

Railway Tunnel between Rokycany and Pilsen

A convertible Herrenknecht multi-mode tunnel boring machine (Ø 9,890?mm) was used to modernize the Czech railway line between Rokycany and Pilsen. The machine excavated two tunnels, each about 4?km...

more
Issue 03/2016 Norway

TBM Quartet for the Follo Line will excavate the longest Railway Tunnel in Scandinavia

In early April 2016 the acceptance of a recently completed Double Shield Tunnel Boring Machine (TBM) with a 9.9 m diameter for Norway‘s infrastructure project “Follo Line” took place at the...

more
Issue 08/2015 Germany

First Tunnel Boring Machine approved for Rastatt Tunnel

The first of two tunnel boring machines (TBMs) for the Rastatt Tunnel by manufacturer Herrenknecht was approved by the customer, the Tunnel Rastatt JV, on December 8, 2015 at the factory in Schwanau....

more
Issue 03/2017 Switzerland

Bözberg Tunnel-TBM should start drive in May

Swiss Railways (SBB) plan to provide a 4 m corridor along the entire Gotthard axis by 2020 in order to be able to transport semi-trailer (articulated) trucks with a height of 4 m by rail. For this...

more