TBM “Lilia” Started Excavation at the Brenner Base Tunnel

On May 2, 2023, the excavation of the east main tunnel from Ahrental southwards began in the H41 Sill Gorge–Pfons construction lot with the start of the tunnel boring machine (TBM) named “Lilia”. Starting from the assembly chamber in the Ahrental valley, which is located just under 1000 m beneath the surface, the TBM will complete its approximately 8.1km long excavation stretch up to the township of Navis.

Assembly of the TBM “Lilia” in the assembly cavern of construction lot H41 Sill Gorge–Pfons
Credit/Quelle: BBT SE

Assembly of the TBM “Lilia” in the assembly cavern of construction lot H41 Sill Gorge–Pfons
Credit/Quelle: BBT SE
On this day, the first segment ring, consisting of six segments, was also installed. The TBM “Lilia” has an excavation diameter of about 10.4 m and a length of about 160 m, including the back-up construction. The weight of the tunnel boring machine is around 2420 t. On-site assembly alone took three months.

BBT CEOs Gilberto Cardola (left) and Martin Gradnitzer (right) with project manager Romed Insam at the cutting wheel of the TBM “Lilia”
Credit/Quelle: BBT SE

BBT CEOs Gilberto Cardola (left) and Martin Gradnitzer (right) with project manager Romed Insam at the cutting wheel of the TBM “Lilia”
Credit/Quelle: BBT SE
The back-up units of a TBM are assigned special tasks to ensure the supply and control of the TBM. In addition to working tools and construction materials, the back-up units also house equipment for personal protection. They contain the installations for placing the segments as well as hydraulic equipment, fans, dust extractors and several transformer systems.

Special rescue containers, equipped with water and emergency aid utensils and supplied with fresh air from the outside, provide refuge for the tunnel workers in dangerous situations. The excavated material is usually transported directly to landfills via conveyor belts.

The second tunnel boring machine "Ida", which will drive the western main bore of the tunnel from the Ahrental towards the south, will start in mid-June 2023.

On-site Segment Production

The segment production for construction lot H41 Sill Gorge–Pfons will take place in the newly constructed hall adjacent to the construction site. In the next 2.5 years, a total of around 51 000 segments will be produced specifically for this construction lot. On-site segment production offers logistical advantages and is environmentally friendly. By producing on site, around 27 000 lorry transports to the construction site can be avoided.

x

Related articles:

Issue 01/2022 Austria

Brenner Base Tunnel: Tender Launched for Pfons–Brenner Construction Lot

If the tendering process goes according to plan, the Pfons–Brenner construction lot is expected to be awarded within 2022. The construction period for the services to be carried out is estimated at...

more
Issue 05/2023

Brenner Base Tunnel: Sandvik DT923i Used for Drill and Blast Excavation of the Main Tunnels

Around 158 km of the total of approx. 230 km of tunnel had been excavated by the end of August 2023. The BBT consists of two 8.1 m wide single track tunnels that run at a distance of 40–70 m. At...

more
Issue 07/2015 Brenner Base Tunnel

Start-Up of the first TBM in the Austrian Part of the BBT

On September 26, 2015, almost exactly a year after works started on the Tulfes–Pfons construction lot, the first tunnel boring machine (TBM) to be used in the Austrian part of the Brenner Base Tunnel...

more
Austria + Italy

Construction Progress at the Brenner Base Tunnel

Start of Tunnelling Works at South Exploratory Tunnel On 29 March 2019 tunnelling work for the fourth drilling of Lot H51 Pfons–Brenner began on the south exploratory tunnel, marked by a drilling...

more
Issue 03/2019 Austria + Italy

Construction Progress at the Brenner Base Tunnel

Start of Tunnelling Works at South Exploratory Tunnel On 29 March 2019 tunnelling work for the fourth drilling of Lot H51 Pfons–Brenner began on the south exploratory tunnel, marked by a drilling...

more