Switzerland

Gotthard Road Tunnel: Main Northern Lot of the Second Tube Awarded

The Swiss Federal Roads Office (FEDRO) has announced its decision to award the Gotthard main northern section to the JV “secondo tubo” (Implenia 60%/Frutiger 40%). The order for the 7.9 km long section, extending up to the lot boundary in the middle of the tunnel, is worth 467 million Swiss francs (485 million euros), construction is scheduled to take place from 2022 to 2029.

The core element of the work is 7.3 km of tunnelling, at a diameter of 12.3 m, using a tunnel boring machine (TBM) and segmental lining. This connects to a 160 m long stretch at the start which will be excavated conventionally. The contract also includes 430 m of conventional tunnel through the northern fault zone, which will be excavated from the 4 km long northern access tunnel that is currently being made. The TBM will later be pulled through this section of the fault zone. After a full revision of the cutterhead the TBM will then complete the excavation through to the lot boundary. The joint venture will also undertake a highly complex excavation for two underground ventilation centres, as well as creating an underground concrete plant and production halls for concrete segments and service ducts in former military caverns.

According to FEDRO, the JV secondo tubo was awarded main northern lot due to “a very good offer in terms of quality and price, making it the most favourable choice. The winning offer was impressive throughout, scoring well or very well on all the award criteria. The key personnel designated for site deployment also rated very highly.”

x

Related articles:

Switzerland

Gotthard Road Tunnel: Main Northern Lot of the Second Tube Awarded

The core element of the work is 7.3 km of tunnelling, at a diameter of 12.3 m, using a tunnel boring machine (TBM) and segmental lining. This connects to a 160 m long stretch at the start which will...

more
Issue 02/2021 Switzerland | Schweiz

2nd Gotthard Tube: Access Shaft Contract Awarded

In mid-March 2021, the Swiss Federal Roads Office (FEDRO) has awarded the 86.6 million Swiss francs (78.5 million euros) contract to build a 4 km access shaft for the second Gotthard tube (Lot 243)...

more
Switzerland

Implenia and Frutiger Win Contract for Sisikon Tunnel, Key Section of the Neue Axenstraße Project

4.4 km Long Road Tunnel Is Excavated by Drill and Blast The contract centres on the single-tube, 4.4 km two-way road tunnel, which the JV will blast through the rock. The JV is also building various...

more
Issue 03/2024 Switzerland | Schweiz

Implenia and Frutiger Win Contract for Sisikon Tunnel

In late June 2024, the cantons of Schwyz and Uri have awarded the contract for the Sisikon Tunnel – lot 200 of the “Neue Axenstrasse” project – to a joint venture (JV) between Implenia (60%) and...

more

Brenner Base Tunnel: Contract Awarded for Lot “H53 Pfons–Brenner”

A few days after the end of tunnelling for the TBM Virginia in the main tunnel east, BBT SE awarded the contract for the construction lot “H53 Pfons-Brenner” in early April 2023. A consortium...

more