Austria

Replacement of the St. Andrä Tunnel on the A 10 Tauern Motorway

In August 2025, preliminary work began away from the main carriageway for the replacement of the almost 40-year-old St. Andrä underpass on the A 10 Tauern motorway. Demolition of the first half of the structure then began in mid-September. Traffic was diverted to the Salzburg-bound carriageway for this purpose.

The St. Andrä Tunnel on the A10 Tauern motorway will be ­replaced by 2028. The total cost of the project amounts to 38 million euros
Credit/Quelle: ASFINAG

The St. Andrä Tunnel on the A10 Tauern motorway will be ­replaced by 2028. The total cost of the project amounts to 38 million euros
Credit/Quelle: ASFINAG

The entire project is planned to take place exclusively from mid-September to Ascension Day in May of the following year, with work on the new tunnel taking place directly on the main carriageway. This will ensure that two lanes in each direction will be open to traffic as normal from the busy spring and summer months onwards. The first construction phase is scheduled for completion on May 13, 2026, followed by construction work off the route until mid-September 2026.

Completion in Summer 2028

By the time of overall completion in summer 2028, not only will the 470 m long tunnel be newly built and equipped with the latest safety features. Two new operational buildings will also be constructed, and the main carriageway will be renovated over a length of one kilometer, as will the Seebach bridge north of the underpass. During the renovation of the open-air section from the Ossiachersee junction to the Villach junction starting in September 2026, ASFINAG will also construct four new water protection facilities.

The new tunnel is necessary due to extensive structural damage that was discovered during inspections. Simply renovating the existing structure would have been more costly and less economical. In total, ASFINAG is investing just under 38 million euros in the renewal of this section of the A 10.

x

Related articles:

Issue 07/2010 Austria

Second Bore for the Tauern Tunnel

The second bore for the Tauern Tunnel on the A10 motorway is 6,400 m long and was driven by mining means within 22 months. It was opened on April 30, 2010 following less than 4 years’ construction,...

more
Issue 02/2021 Brenner Base Tunnel | Brenner Basistunnel

Isarco River Underpass Construction Site: Ground Freezing for the First Main Tunnel

In the municipality of Fortezza works on the Isarco River Underpass construction site, which is the southernmost construction lot of the Brenner Base Tunnel, are proceeding at full speed. The complex...

more
Issue 07/2011 Austria

The twin-bore Tauern Tunnel commissioned

The 6.4 km long Tauern Tunnel (1971/1975) on the A10 motorway was provided with a second bore (2006/2010) following the accident in 1999 while the existing bore was redeveloped at the same time. In...

more
Issue 06/2020 Italy

Brenner Base Tunnel: First Breakthrough at the Isarco River Underpass

Starting from one of the four shafts built on the Isarco River Underpass construction site, the underlying aquifer and alluvial deposits below the riverbed were frozen by injecting liquid nitrogen...

more
Issue 08/2014 Italy?/?Brenner Base Tunnel

Contracts signed for the Isarco River Underpass

At the end of a public tender procedure published at the European level, BBT SE awarded the contract for executive planning and works for the Isarco River Underpass to the temporary consortium made up...

more