Austria

Brenner Base Tunnel: BBT SE Terminates Construction Contract with ARGE H51 Pfons–Brenner

According to Brenner Basistunnelgesellschaft (BBT SE), despite intensive negotiations, no agreement could be reached with the contractor, ARGE H51, regarding contractual differences of opinion on construction lot H51 Pfons–Brenner – the southernmost section of the project area in Austria, which is about 15 km long. On 27 October 2020, BBT SE sent a letter to ARGE H51 (Porr Bau GmbH, G. Hinteregger & Söhne Bau GmbH, Condotte S.p.A. and Itinera S.p.A.) to terminate the construction contract. Porr AG claimed that the BBT SE’s withdrawal from the contract to build the Pfons–Brenner lot was plainly unlawful. The contract would thus remain valid and Porr AG would take all steps necessary to protect its rights.


The BBT SE’s Perspective:

“The final refusal to carry out the contractually agreed works and the subsequent loss of trust has unfortunately forced us to dissolve the contract with ARGE H51. Even with the prospect of the termination of the contract, ARGE H51 did not change its position and decided to make public its contractual interpretation. To ensure that the works for the Brenner Base Tunnel can continue as quickly as possible, an in-depth analysis of the entire project has already been started with the aim of launching a new tender procedure”, the two CEOs of BBT SE, Gilberto Cardola and Martin Gradnitzer, explained.

 

 “Lack of Constructive Cooperation”

Shortly after the award of the largest construction lot in the Austrian project area, major differences of opinion had arisen between the contracting authority, BBT SE, and ARGE H51. BBT SE criticised that the ARGE H51 went public with their view of the situation “in a one-sided and very simplistic way, only mentioning the segment rings issue”.

BBT SE notes, however, that the problems did not concern technical issues, such as the segment rings: “The main reason for the dissolution of the contract was the final refuse to carry out the works and the delays occured with regard to some essential contractual aspects.”

 

The Dispute Over the Segment Rings

The invitation to tender, which was carried out under the technical direction of the former Board of Directors, provided that responsibility for planning and building the segment rings with a minimum of 40 mm of thickness lied with the contractor. Only after the award of the contract, ARGE H51 stated that the 40 cm segment ring – offered by ARGE H51 itself – was not feasible and requested either a thicker segment ring or the reduction of the loads at the expense of BBT SE.

BBT SE stated, that, as a contracting authority, they had repeatedly proposed solutions to the technical problems raised by ARGE H51 regarding the segment ring: “BBT SE very much regrets that ARGE H51 did not accept its support and that this led to serious delays in the Pfons–Brenner construction lot”

 

“We Had No Other Choice”

The two CEOs of BBT emphasised “As new CEOs we took over a difficult construction lot and worked hard for almost a year to find a solution. A contract worth a billion cannot be dissolved in a light-hearted manner; however, we had no other choice, because even the last solution proposed by ARGE H51 on October 5th 2020 was not viable from a technical and legal point of view.”

Now that the decision on the H51 lot has been made, BBT SE will complete the ongoing evaluation of the construction timetable, assess all possible measures and complete an updated construction program. On this basis it is currently being evaluated if the risk provision is sufficient to cover additional costs resulting from the dissolution and the adjustment for inflation.

 

 

Porr AG’s Perspective:

Karl-Heinz Strauss, CEO of Porr AG, stated “This unilateral termination of the contract is clearly illegal. The contract between consortium H51 and BBT SE is still valid, even in the event of a new contract being awarded”. University professor Dr. Andreas Kletečka came to the same conclusion when writing his legal opinion. This would have far-reaching consequences: “In the event of an illegal termination, BBT would have to fulfil the contract with the consortium in any case and possibly also a second contract with a new contractor. BBT would not only have to pay for the loss of profits, but also cover all costs for the ongoing availability of the entire consortium workforce and its technology. This in itself may come to almost as much as the original contract sum", said Kletečka.

 

“Failures of Management and Supervision Are Swept Under the Rug”

According to Porr, not only is the termination of the contract not legally covered, it is also highly irresponsible towards the Austrian taxpayers. It would make a delay of several years to this project inevitable, along with cost increases in the millions. Porr stated they had always been ready to render the requisite services and discuss any issues in addition to offering technologically sound solutions at no additional cost.

Strauss underlined that if BBT were to take safety concerns seriously, the Management and Supervisory board would have to admit that they had set parameters in the tender for cost reasons that would make the safe construction of the tunnel impossible if the applicable technical standards were upheld. “But since it is obvious that what is not allowed cannot be the case, they now want to save themselves by illegally terminating the contract”.

 

“The Contract Remains Valid”

Porr AG, whose participation in the consortium H51 Pfons–Brenner is worth around half of the contract value of 966 Million euros has announced to take every step necessary to protect its rights. “The contract is valid. That’s why we won’t be taking the rap for failures of management and of supervision and why we insist that BBT take responsibility for the damages incurred”, said Strauss.

x

Related articles:

Issue 06/2020 Austria

Brenner Base Tunnel: BBT SE Terminates Construction Contract with ARGE H51 Pfons–Brenner

The BBT SE’s Perspective: “The final refusal to carry out the contractually agreed works and the subsequent loss of trust has unfortunately forced us to dissolve the contract with ARGE H51. Even...

more

Brenner Base Tunnel: Contract Awarded for Lot “H53 Pfons–Brenner”

A few days after the end of tunnelling for the TBM Virginia in the main tunnel east, BBT SE awarded the contract for the construction lot “H53 Pfons-Brenner” in early April 2023. A consortium...

more
Issue 01/2022 Austria

Brenner Base Tunnel: Tender Launched for Pfons–Brenner Construction Lot

If the tendering process goes according to plan, the Pfons–Brenner construction lot is expected to be awarded within 2022. The construction period for the services to be carried out is estimated at...

more
Issue 02/2020

Crawler-Mounted Jaw Crushers Process Excavated Material in the Pfons–Brenner Lot of the BBT

Two jaw-crusher machines and a feeder unit, all supplied by Swiss manufacturer GIPO, are in front-line use on the Austrian side of the largest and most southerly construction sector of the new Brenner...

more
Austria + Italy

Construction Progress at the Brenner Base Tunnel

Start of Tunnelling Works at South Exploratory Tunnel On 29 March 2019 tunnelling work for the fourth drilling of Lot H51 Pfons–Brenner began on the south exploratory tunnel, marked by a drilling...

more