Branich Tunnel – Aggregates assure Reaction Capacity at below-zero Temperatures

Since December 2011, construction work on the 1.8 km long Branich Tunnel has been forging ahead much to the delight of local residents of Schriesheim in Baden. 1,000 of the 1,800 m had been completed in late January 2013. The breakthrough will probably follow in June 2013. The tunnel is part of the “Schriesheim Bypass” project. The L536 is being upgraded over a length of 3.3 km. The Land of Baden-Württemberg represented by the administrative district of Karlsruhe is investing some € 85 million for the work to be carried out with around € 58 million accounted for by the Branich Tunnel.

The tunnel is being driven by trenchless means. In addition to the pure tunnelling activities, 5 emergency exits are being set up, which lead into 2 separate evacuation tunnels.

The construction work has gone down well with the population because a survey showed that the scheme would result in traffic in the old part of Schriesheim being reduced by almost 70 %. The obvious advantages for local residents in Schriesheim and outstanding cooperation with the responsible contractor Züblin, Stuttgart prompted the tunnel’s sponsor Brigit Ibach-Höfer at last year’s St. Barbara ceremony to speak of a familiar relationship between the citizens of the town and the construction workers on-site.

For preparing the concrete 390 kg CEM II 52.5 N Dyckerhoff, Amöneburg, shotcrete quality C 30/27 was used. The fresh concrete is delivered to the construction site by 3 different ready-mixed concrete plants (TB Kurpfalzbeton, TB Kühner and TB Leutershausen).

Hard frost prevailed particularly during the initial stages. Notwithstanding the products from the Gecedral® 100 range from Messrs. BK Giulini GmbH, Ludwigshafen/D assured the shotcrete’s reaction capacity even at these sub-zero temperatures. As a result the driving operations were able to progress quickly in spite of the inclement weather conditions; early strength class J 2 was attained without difficulty and safety during the excavation was assured all the time.

x

Related articles:

Issue 2017-08 Austria

Conference: Shotcrete 2018

The 12th conference on shotcrete with parallel exhibition will take place at the Alpbach Congress Centrum in Tyrol, Austria, on January 11–12, 2018. Conference chair is Prof. Wolfgang Kusterle,...

more
Issue 2016-02 Germany

Flexible Formwork System for the Branich Tunnel

In summer 2016, the 1796 m long single-bore Branich Tunnel is due to open as part of the bypass for the small German town of Schriesheim, north of Heidelberg on the Bergstraße. About 1600 m are...

more
Issue 2011-07 Albania/Kosovo

Thirra Highway Tunnel secured

Once completed, the new Albania-Kosovo Highway will link Kosovo with the seaport of Durres on the Adriatic Sea, crossing Albania. The travel route will then be much easier and shorter, thus...

more
Issue 2019-03 Sika Deutschland

Full-Area Grouting behind existing Shotcrete Layer

After more than 60 years of use, refurbishment of the road tunnel between Neuhaus and Spitzingsee bei Schliersee, Germany, was urgently necessary. The waterproofing directly behind the shotcrete inner...

more
Issue 2015-01 Austria

New Semmering Base Tunnel: Gloggnitz Preliminary Work finished

The 27.3 km long New Semmering Base Tunnel (SBTn) is a major element of the new Austrian southern rail route. Its two bores are to be linked every 500 m by cross-passages and an emergency halt with...

more