Nepal

Nepal’s first TBM bores Tunnel for Irrigation & Hydroelectric Project

Nepal welcomed its first TBM ever in summer 2017: a 5.06 m diameter Double Shield machine for the Bheri Babai Diversion Multipurpose Project (BBDMP). The Robbins TBM underwent its factory acceptance testing in July 2017 before it was shipped to the jobsite in the Siwalik Range, part of the Southern Himalayan Mountains. Pre-construction included laying gravel onto rural roads and excavating wells for drinking water. Originally scheduled for November 2017, the TBM for the 12.2 km tunnel was launched on October 14.

Bheri Babai Diversion Multipurpose Project

The BBDMP is one of Nepal’s 11 National Pride Projects – prioritized plans sanctioned by the Government of Nepal to further develop the mainly rural country. It is expected to help aide the food crisis in the mid-western region of Nepal by increasing agricultural yields and invigorating socio-economic development in the region.

This project will irrigate 60 000 hectares of land, benefitting an estimated 30 000 households. It will divert 40 m3 of water per second from Bheri River to Babai River under a head of 150 m using a 15 m tall dam, providing year-round irrigation in the surrounding Banke and Bardia districts. The water will also be used for hydroelectricity, with a generating capacity of 48 MW benefiting the country with 2 billion Nepalese rupees (16 million Euros) annually.

Tunnelling in the young Geology of the Himalayas

Contractor China Overseas Engineering Group Co. Ltd. Nepal Branch (COVEC Nepal Branch), represented by China Railway No.2 Engineering Co., Ltd Chengtong Branch, is responsible for the headrace tunnel and is aware of the challenges associated with tunneling in tough geology. The Siwalik range is projected to consist of mainly sandstone, mudstone and conglomerate, requiring a TBM that can withstand squeezing ground, rock instability, possibly high ingress of water and fault zones. Maximum cover above the tunnel is 820 m.

Due to the challenges in the young geology of the Himalayas, Difficult Ground Solutions (DGS) have been incorporated into the machine’s design. A stepped shield has been designed to move through squeezing ground. Robbins Project Engineer Missy Isaman talked about the DGS features incorporated into the TBM: “There is a probe drill in the rear that probes through the gripper shield in
14 places. We added ports in the forward shield for drilling too. There are eight ports around the circumference for hand drilling. There are also six ports in the top 100 degrees of the shield for forepoling.” She further noted that no equipment was ordered for either of the forward shield drilling options, but it’s easier to add the ports to the shield now, in case more comprehensive drilling is needed later in the bore. Other machine modifications included 35 mm (70 mm on the diameter) of possible overcut for gage cutters, and additional ports in the forward shield for dewatering. Muck removal is achieved by muck cars. The tunnel is lined with hexagonal precast concrete segments.

A faster Rate of Advance

The project owner, the Government of Nepal’s Ministry of Irrigation (MOI), has chosen a TBM over the traditional method of drill & blast due to the faster mobilization and rate of advance offered by mechanized tunnelling. “The reason a TBM was chosen for this project was because using d&b method could have taken at least 12 years for project completion. This was due to there only being one excavation heading with no possibility of launching multiple operations using adit tunnels,” said Robbins General Manager for Nepal, Prajwal Man Shrestha. More generally, Mr. Shrestha saw the project as a way to prove that TBMs can indeed take on complex Himalayan rock. “Since the Himalayan range has a young geology and not much has been surveyed yet, the use of newer technology is looked upon with slight apprehension. The first few TBM projects and additional surveys will show how suitable TBM technology will be for the Himalayan Range.”

x

Related articles:

Nepal

TBM Launch for the Sunkoshi Marin Diversion Multipurpose Project in Nepal

Granitic Rock With Maximum Overburden of 1320 m The headrace tunnel is being bored through granitic rock with maximum overburden of 1320 m. Geological conditions may include squeezing ground,...

more
Issue 03/2011

Double Shield TBM for Indian Water Tunnel

Project Background Eastern areas of India’s Andhra Pradesh state receive only 20 cm of rainfall per year - an amount comparable to Africa’s Kalahari Desert. The Andhra Pradesh Irrigation Department...

more
Issue 05/2011

Palomino Project: First Double Shield TBM in the Dominican Republic

1 Island Pioneers The “Anacaona” Double Shield TBM (4.5 m diameter) (Fig. 1) started its work where Columbus’ first great voyage of discovery ended in 1492. On the Caribbean island of Hispaniola,...

more
Issue 03/2022 China

Challenging Drive at China’s Yin Han Ji Wei Water Diversion Project Completed

The ground, consisting of mainly quartzite and granite, was estimated to have a rock hardness of between 107 and 309 MPa UCS, with high abrasivity and a maximum quartz content of 92.6%. During...

more
Issue 01/2011 China

Hard-Working TBM breaks through at Pinglu Tunnel

A veteran Double Shield completed one of the world’s longest single-drive TBM tunnels, at 25.4 km (15.8 mi), on November 14, 2010 (Fig. 1). The 4.8 m (15.7 ft) diameter machine bored the Pinglu...

more