New Railway Line Gelnhausen–Fulda: 28 km of the Route will run in Tunnels

Longest tunnel on this line planned to run over a distance of 9.5 km

After weighing the advantages and disadvantages, German Railways (DB) announced a preference for a new line between Gelnhausen and the Fulda–Würzburg high-speed line at the Dialogforum Hanau–Würzburg/Fulda on 15 June 2018 and will apply for this so-called “Variant IV” in a planning approval process in early 2019.

Thanks to the high proportion of tunnels of about 28 km out of the total line distance of 44 km, the line of Variant IV will have little impact on people and environment and will above all relieve the towns and villages in the Kinzigtal from the noise of goods traffic.

The longest tunnel on this line is planned to run over a distance of 9.5 km between Schlüchtern and Mittelkalbach. For passenger services, the journey time between Frankfurt am Main and Fulda will be shortened by eleven minutes. A link to the existing line is provided in Schlüchtern.

G. B.

x

Related articles:

Germany

New Railway Line Gelnhausen–Fulda: 28 km of the Route will run in Tunnels

After weighing the advantages and disadvantages, German Railways (DB) announced a preference for a new line between Gelnhausen and the Fulda–Würzburg high-speed line at the Dialogforum...

more
Issue 02/2010

Austria Koralm Railway: Inviting Submissions for the longest Tunnelling Contract Section

The Koralm Railway is the extension of the trans-European corridor VI and part of the axis from Danzig via Warsaw and Vienna to Triest, Venice and Bologna, in other words the link between the Baltic...

more
Issue 03/2016 Norway

TBM Quartet for the Follo Line will excavate the longest Railway Tunnel in Scandinavia

In early April 2016 the acceptance of a recently completed Double Shield Tunnel Boring Machine (TBM) with a 9.9 m diameter for Norway‘s infrastructure project “Follo Line” took place at the...

more
Issue 07/2013 Germany

Safely through railway tunnel

The Deutsche Bahn operates a 4-stage safety concept for all its tunnels embracing the measures prevention, incident reduction, self-rescue and third-party rescue. At present, the DB maintains 6...

more
Issue 05/2011 Austria

Koralm Tunnel: Work starts on main Section

The Koralm Tunnel represents the core of the new 130 km long Koralmbahn, being set up between Graz and Klagenfurt, a twin-track high-speed line designed for speeds of up to 200 km/h estimated to cost...

more