North Link Project: Refurbished TBM tackles Urban Seattle Tunnel

Tucked away on a small jobsite in a quiet neighbourhood bordering a busy interstate highway, a Robbins Earth Pressure Balance (EPB) machine underwent Onsite First Time Assembly (OFTA). The OFTA method allows for TBMs to be initially assembled onsite, and results in time and cost savings to the contractor. On November 17, 2014 the 6.65 m (21.8 ft) TBM rumbled to life and began its journey south into the city of Seattle, Washington, USA.

The machine, for contractor JCM North Link LLC (a joint venture of Jay Dee, Coluccio, and Michels) is excavating for the North Link Project, which is an...

Related articles:

Issue 2012-08 The Robbins Company

In June 2012 the Robbins Company celebrated at the NAT 2012 (North American Tunnelling Conference) in Indianapolis, Indiana/USA 60 years of Tunnelling. Taking this chance, Lok Home found time for an...

more
Issue 2011-04 Switzerland

The Autobahn A5 Biel bypass in the Canton of Bern closes one of the last remaining gaps in Switzerland‘s national road system, and is subdivided into a west and an east link, both around 5?km in...

more
Issue 2018-01 Nepal

Nepal welcomed its first TBM ever in summer 2017: a 5.06 m diameter Double Shield machine for the Bheri Babai Diversion Multipurpose Project (BBDMP). The Robbins TBM underwent its factory acceptance...

more
Issue 2011-01 China

A veteran Double Shield completed one of the world’s longest single-drive TBM tunnels, at 25.4 km (15.8 mi), on November 14, 2010 (Fig. 1). The 4.8 m (15.7 ft) diameter machine bored the Pinglu...

more
Obituary

In total he filed 11 U.S. patents and 56 foreign patents in the field of underground mechanical excavation, and ultimately won the 2009 Benjamin Franklin Medal in Engineering for his contributions. He...

more