Schlüchtern Tunnel: Adding Evacuation Tunnels without discontinuing Rail Traffic

Immediately after the New Schlüchtern tunnel was completed a change in the safety regulations deemed it necessary to build 4 additional evacuation tunnels. These cross-passages were added to the segment-lined main tunnel from the outside without discontinuing rail traffic in order to avoid a prolonged construction period.

Starting Position

The Old Schlüchtern Tunnel is a rail tunnel on the main Frankfurt-Fulda line. It is 3,575 m long and was opened in 1914. Plans were made to completely renew the tunnel following extensive damage to the old masonry vault. Towards this end, it was first intended to produce a new tunnel parallel to the old one, then operate it with 2 tracks after completion and subsequently renovate the old tunnel. The New Schlüchtern Tunnel was driven with a shield from April 2007 and opened in April 2011. Fig. 1 shows the south portals of the 2 Schlüchtern tunnels. While driving the new bore, 3...

Related articles:

Issue 2011-07 Germany

Redeveloping the Schlüchtern Tunnel

The New Schlüchtern Tunnel is nearly 4 k m long and possesses 9 m internal diameter. It was driven using a tunnel boring machine (TBM) at a distance of 50 to 90 m from the existing tunnel [1-4]. As...

more
Issue 2014-03 Germany

Schlüchtern Tunnel: Two Bores for a busy Rail Route

The 3,576 m long Old Schlüch- tern Tunnel on the main line between Frankfurt and Fulda was opened in 1914. With a total of 260 passenger and goods trains daily it was one of Germany’s busiest rail...

more
Issue 2010-07 Austria

Second Bore for the Tauern Tunnel

The second bore for the Tauern Tunnel on the A10 motorway is 6,400 m long and was driven by mining means within 22 months. It was opened on April 30, 2010 following less than 4 years’ construction,...

more
Issue 2011-03 Switzerland

Gotthard Base Tunnel: Drive concluded

On March 23, 2011 at 20 past 12 noon the tunnel boring machine broke through from the Faido western bore into the Sedrun part-section (title page); in this connection the deviations from the intended...

more
Issue 2013-04 Switzerland

Eyholz Tunnel: North Bore broken through

The Eyholz Tunnel between Stald­bach and Grosshüs serves the A?9 motorway to circumvent Visp in the Canton of Valais/CH, passing in the south. It consists of 2 bores set some 30 m apart with 15...

more