Special Demands for Pipe Jacking beneath Rail Tracks

Generally speaking trenchless construction methods are applied for routing pipelines beneath Deutsche Bahn AG rail tracks, with special demands posed on planning and execution. Owing to constraints imposed by planning, deviations from the pertinent regulations are sometimes inevitable. Consequently, the same safety level must be reached by means of separate regulations and conditions (UIG “Corporate Approval”, ZIE “Approval in individual Case”) of the DB Netz AG and the German Federal Railway Authority (EBA) combined with extended quality assurance strategies. In this connection, emphasis is placed on planning the execution and adapting the driving method to the project’s marginal conditions as well as on involving all those participating in construction.

Motivation

The need to modernise and expand the existing line networks of the telecommunications and energy supply companies is growing in keeping with the advance in infrastructural networking of cities and municipalities as well as increasing urban population densities. Frequently, additional pipelines and those requiring renewal cross existing Deutsche Bahn AG rail routes so that codes of practice relating to the railways must also be observed in planning and execution along with engineering standards. It is often not possible to alter the course of pipelines on account of technical...

Related articles:

Issue 2012-02 New Brochure

AlpTransit Gotthard

New Transport Routes through the Heart of Switzerland 12/2011: 48 pp. (DIN A4) with 90 Ills. + Tables. Available from: AlpTransit Gotthard AG, Lucerne – www.alptransit.ch Since driving operations...

more
Issue 2017-01 Track Crossings

STUVA Research to improve Traffic Safety for Pedestrians and Cyclists

Findings designed to improve the safety of pedestrians and cyclists when using railway crossings are to emerge from a research project (FE-No. 82.0613/2014). The project was commissioned by the...

more
Issue 2010-02 Austria

Safety technical Equipment for the Arlberg Railway Tunnel

One of the Austrian Federal Railways’ (ÖBB Infrastruktur AG) biggest safety technical projects is being tackled in the 10.5 km long twin-track Arlberg railway tunnel (built between 1879 and 1894)...

more
Issue 2012-07 Switzerland

Zurich Weinberg Tunnel: Installing the Rail Technology

Along with the underground through station – Löwenstraße – the roughly 4.8 km long, twin-track Weinberg Tunnel in Zurich forms the core of the SBB Zurich Cross Rail (DML) project, which connects...

more
Issue 2015-01 Switzerland

Gotthard Base Tunnel: Track Installation completed

At the end of October 2014 the final sections of track were laid in the Gotthard Base Tunnel (GBT). This means that the world’s longest rail tunnel can now be negotiated over its entire 57 km length...

more