Jagdberg Tunnel on the A4 Motorway

Jagdberg Tunnel on the A4 Motorway Eisenach–Görlitz

Untertiteltext Englisch

A report on the start of construction on the Jagdberg Tunnel in Thuringia was provided at length in tunnel 1/2009 p. 8 ff. The following article follows on from presenting the project launch and concentrates on excavating the tunnel, the geology and the effects of the drive that was undertaken.

1 Introduction

The moment had arrived on August 27, 2009. Practically almost 9 months after work officially began on the tunnel on September 26, 2008, the official breakthrough of the first of the 2 roughly 3,100 m long tunnel bores, the southern bore, was ceremoniously celebrated. A week later on September 3, 2009 the northern bore followed. As a result contrary to all forecasts the crown drives for the southern and northern bores were completed some 9 months earlier than predicted (Fig. 1).

Both bores were driven with a slight time gap by drill+blast with an advancing crown in a continuous...

Related articles:

Issue 2010-03 Jagdberg Tunnel on the A4 Motorway

Jagdberg Tunnel on the A4 Motorway Eisenach–Görlitz

1 Introduction The moment had arrived on August 27, 2009. Practically almost 9 months after work officially began on the tunnel on September 26, 2008, the official breakthrough of the first of the 2...

more
Issue 2010-07 Switzerland

Gotthard Base Tunnel: TBM restarts in Faido west tunnel

On 4 March 2010 excavation had to be stopped in the west tunnel of the Gotthard Base Tunnel some 9 km from the Faido multifunction station due to a rock inrush, and exploratory bores had to be...

more
Issue 2010-04 Switzerland

Gotthard Axis – Situation in March 2010

The CEO of the AlpTransit Gotthard AG Renzo Simoni reported on progress achieved in building Switzerland’s biggest construction project during the premiere of the 2009 AlpTransit annual film on March...

more
Issue 2014-02 Turkey

Yamanli II: In tough Turkish Ground

In December 2013, a 4.3 m (14.1 ft) Robbins Double Shield TBM broke through according to plan after boring a 9.3 km (5.8 mi) tunnel in Turkey’s Adana Province for the Yamanli II Hydroelectric...

more
Issue 2010-04 Austria

Second Bore for Bosruck Tunnel

The Asfinag as operator of the motorway in Austria has commissioned the construction of a second tunnel bore with 5 breakdown bays and 11 cross-passages (6 of them negotiable with vehicles) for the...

more