Switzerland

Gotthard Base Tunnel: Clearing and Rescue Operations Will Last Until End of September 2023

On 10 August 2023, a cargo train derailed in the west tube of the Gotthard Base Tunnel. Major material damage was caused. The repair work will take several months. 22 wagons and two locomotives were removed from the tunnel by 6 September. At that time, 8 wagons were still in the tunnel. Several wagons were so badly damaged that they had to be dismantled in the tunnel before they could be removed. Since 23 August, freight traffic has been allowed to pass through the undamaged east tunnel again.

No Official Information Yet on Cause of Derailment and Extent of Damage

The incident in the Gotthard Base Tunnel occurred in the early afternoon at the Faido multifunction station. The freight train involved was travelling north. The derailment caused severe damage to the track system and a lane-changing gate in the Gotthard Base Tunnel. SBB has not yet given any information about the cause of the accident or the extent of the damage. The derailment is said to have been caused by a broken wheel. The Swiss Transportation Safety Investigation Board (STSB) is examining the causes of the damage.

The extensive clearing and recovery work at the accident site in the west tunnel is expected to last until the end of September. Work is being carried out in two shifts, seven days a week. 22 wagons and two locomotives have already been removed from the tunnel. Currently, 8 wagons are still in the tunnel. Several wagons were so badly damaged that they have to be dismantled in the tunnel before they can be removed. The wagons are being salvaged via the south portal, which is about 15 km away from the accident site. For this purpose, a temporary track had to be constructed in places.

Parallel to this work, the SBB is working on a detailed survey of the damage caused. The aim is to be able to start repairing the damaged railway facilities immediately after the end of the clearance and salvage work at the end of September.

Freight Traffic Runs Through Base Tunnel With Restrictions

Since 23 August, four freight trains at a time have been able to travel through the undamaged east tunnel. These are followed by four freight trains from the opposite direction. Currently, about 90 of a maximum of 100 freight trains per day travel through the Gotthard Base Tunnel. An additional 15 to 20 freight trains per day run via the Gotthard panorama route. Passenger trains are still diverted via the Gotthard Panorama Route and are thus an hour longer on the way.

x

Related articles:

Issue 06/2023 Switzerland | Schweiz

Gotthard Base Tunnel: Serious Damage, Normal Operation Expected as of September 2024

The derailment of a cargo train in the Gotthard Base Tunnel on 10 August 2023 caused considerably more serious damage than initially assumed. The repair work will therefore take much longer than...

more
Switzerland

Gotthard Base Tunnel: Serious Damage, Normal Operation Expected as of September 2024

SBB has estimated that the tunnel will not be fully reopened for passenger and cargo trains until September 2024. From the timetable change on 10 December 2023, SBB intends to increase capacity for...

more
Issue 07/2014

Gotthard Base Tunnel: Control Technology

The Gotthard Base Tunnel consists of two parallel, 57 km long single-track bores, which are linked to each other by means of 40 m long cross-passages at 325 m gaps. Altogether, the tunnel system with...

more
Issue 04/2010 Dachzeilentext Englisch

Rail Technology in the Gotthard Base Tunnel

Untertiteltext Englisch

The rail technology embraces all components and systems, which belong to the “actual rail technical system”: the track, electric installations for supplying power for the rail technology and the...

more
Issue 08/2015 Switzerland

Test Operation in the Gotthard Base Tunnel

Since early October 2015, the test operation phase in the Gotthard Base Tunnel has been in full swing. Numerous test runs have already been performed. Until May 31, 2016, around 5000 test runs are...

more