Pilot Project: Applying the Tunnel-in-Tunnel Method on DB electrified Routes

This report deals with the refurbishing of the Petersberg Tunnel. In this connection, for the first time within the scope of a pilot project, the tunnel-in-tunnel method was applied on an electrified line belonging to the DB. The tunnel cross-section was enlarged within the scope of the excavation. These activities were executed with the aid of a tunnel enlargement system (TES). Towards this end, the existing overhead line for electrification of the route had to be integrated in the excavation. Once the driving operations had been completed, the tunnel inner shell made of reinforced concrete was produced. Thanks to this project the spectrum of refurbishing tunnels has been considerably expanded, as the method can be deployed for other projects on the electrified route network.

1 Deploying the Tunnel-in-Tunnel Method

for Deutsche Bahn

The tunnel-in-tunnel method has already been successfully tried out and further developed on several non-electrified routes in regional transportation. In this method, the tunnel cross-section is expanded by drill+blast or cutting tools with trains services still operating and a new reinforced concrete inner shell installed according to the valid requirements of the code of practice. When construction starts, the track is relocated to the centre of the tunnel and services run in alternating directions for the duration of the scheme....

Related articles:

Issue 2011-04 Austria

The Lower Inn Valley line Tunnel shell completed

The Austrian Federal Railways (ÖBB) project engineers working on the new Lower Inn Valley line awarded themselves an early Christmas present in late 2010, with the application, at Radfeld on December...

more
Issue 2022-03 Germany

U5 Europaviertel, Frankfurt: Tunnel Excavation Completed

The difficult conditions of inner-city tunnelling posed great challenges for all those involved. For the first time, a tunnel was constructed in Frankfurt a. M. using mechanised tunnelling. In...

more
Issue 2018-02

New Bözberg Tunnel: Structural Measures when Tunnelling in squeezing Rock

1 Introduction The new Bözberg Tunnel with a total length of roughly 2.7 km is the longest single element among the structures on the 4-Metre Corridor, which were largely driven mechanically using a...

more
Issue 2014-03 Germany

Schlüchtern Tunnel: Two Bores for a busy Rail Route

The 3,576 m long Old Schlüch- tern Tunnel on the main line between Frankfurt and Fulda was opened in 1914. With a total of 260 passenger and goods trains daily it was one of Germany’s busiest rail...

more
Issue 2016-08 Germany

Construction start for S-Bahn Tunnel Gateway Gardens, Frankfurt

On the approx. 35 hectare site of the former American military housing estate Gateway Gardens in close proximity to Frankfurt Airport, a new city quarter is being developed with office and conference...

more