Challenge in Tunnel Redevelopment

General Renovation of the
Rendsburg Canal Tunnel

The Rendsburg Canal Tunnel under the North-Baltic Sea Canal was opened for traffic in 1961. Since then the canal tunnel has been an important, practically indispensable part-section of the north-south axis along the B77 through Schleswig-Holstein – used by around 50,000 vehicles per day. After 50 years it is now time to thoroughly renovate the structure in spite of continuous maintenance measures over this period. In the process signs of wear will be removed, which could not be remedied through regular operations while traffic is still running. Redevelopment is scheduled to last 3 years. It is to be tackled in 3 phases. The conception for repairing the concrete was devised by the Federal Waterway Engineering and Research Institute (Bundesanstalt für Wasserbau) in Karlsruhe in conjunction with the Institute for Construction Research at the RWTH – Aachen University. The execution of planning for engineering and road construction as well as the production and plant engineering was provided by the Ingenieurbüro Pöyry Infra, Hamburg; the planning for restoring the concrete by the Ingenieurbüro Oemig und Partner from Kiel. Construction is being carried out by the Hamburg branch of the JV Züblin-Wisag.

The Rendsburg Tunnel is no sole instance: an increasing number of tunnels and bridges are reaching an age signifying that general redevelopment is essential. Hernani Esteves, the Group Manager for Cathodic Corrosion Protection at the Ed. Züblin AG has a key role to play in redeveloping the Rendsburg Canal Tunnel. He now explains the tasks, challenges and recognitions, which resulted for all those involved in restoring the structure.


Redeveloping a canal tunnel represents a special task: what is the technical challenge, the special factor relating to the redevelopment of the Rendsburg Tunnel?

Redeveloping a tunnel with traffic still running is in itself a challenge. Furthermore various activities have to be coordinated. Apart from restoring the reinforcement in the concrete and the application of cathodic corrosion protection, signal technology, drainage, ventilation and lighting have to be dealt with. Furthermore very constricted space conditions prevail in a service passage, which is only some 1.20 m wide – something which makes work a real challenge.


Just how far is Züblin as the responsible contractor involved for instance in the concrete renovation?

The tunnel redevelopment conception was worked out by Pöyry Infra GmbH as general planner and then appropriate tenders were invited by the client. Züblin was commissioned to fulfil a part of the contract and as responsible contractor is not involved in the conception.


What is to be understood under the term “special fire protection mortar”, which is to be placed on the tunnel walls? Is this some new development? Have you already gained experience with it?

It is customary to apply fire protection mortar in tunnels to safeguard fire protection. This is already known from past projects. The main task of a fire protection mortar is to secure a concrete covering on top of the steel reinforcement in the tunnel walls as the outermost layer. In this way the tunnel is able to withstand a fire structurally over a given period, so that those affected are given the time to escape. Special mortars of this kind have to be tested according to DIN 4102, Part 4. Towards this end the mortar is tried out in a fire test – with the duration and temperature geared to a special fire curve.


What does “cathodic corrosion protection” actually mean? Can you please briefly explain this method? Why was it decided to apply it?

Cathodic corrosion protection is an electro-chemical method, a protective current is fed into the concrete by means of an electric current anode, which protects the steel reinforcement integrated in the concrete permanently from corrosion. Towards this end the anode is connected to the positive pole of a rectifier unit and the reinforcement to the negative one. The protective current is fed in by the surrounding tension; corrosion is either reduced to a negligible amount or prevented entirely.


Tunnels have been criticised because in the event of danger – for example during a fire – the persons located in the tunnel find it rather difficult to be evacuated safety: it is often practically impossible to find one’s way on account of smoke, the air becomes bade, there’s not enough oxygen to reach the tunnel exit. Which measures have been taken in the Rendsburg Tunnel in order to ameliorate such hazardous situations?

By renovating the ventilation as well as the lighting technology escapeways will be clearly designated following the redevelopment phase and the ventilation in the tunnel bore can be adjusted to cope with an emergency situation as well thanks to continuous video and air quality monitoring. In safety technical terms the tunnel will be generally restored thus corresponding to the latest state of the art.


The Rendsburg Tunnel now some 50 years old is certainly not the latest state of the art. How many tunnels of similar age and similarly furnished are there still in Germany, which also require to be renovated? Will it be possible to gather findings through working on the Rendsburg Tunnel, which will help with further projected redevelopments?

I really couldn’t say exactly how many tunnels of a similar age and type there are in Germany at present. However a wealth of experience will certainly become available through the work on the Rendsburg Tunnel, which will be useful for similar projects in future. Here in fact we are profiting from experience we were able to gather from completed tunnel projects.


How much would you say has to be invested on average in redeveloping a tunnel? How long is it expected to take?

The costs for redeveloping a tunnel depend on the site, age and the question as to just how thorough the renovation process is. A period of some 3 years has been allocated to restore the Rendsburg Tunnel.


Are you, is your company taking part in the econstra construction engineering fair in Freiburg in October? If so what are you expecting from it?

Yes, Züblin’s taking part. Apart from, exchanging know-how with other experts we hope to be able to provide interested visitors with insights of our world and present an opportunity to respond to questions directly and conduct interesting discussions.


x

Related articles:

Tunnel Refurbishment

First Tunnel Refurbishment with Cathodic Corrosion Protection in Germany

After the Hamburg Elbe Tunnel dating from 1912, the two-tube 640 m long Rendsburg Canal Tunnel, which opened in 1961, was the second underwater tunnel built in Germany for road traffic. Now it is the...

more
Issue 05/2019

First Tunnel Refurbishment with Cathodic Corrosion Protection in Germany

After the Hamburg Elbe Tunnel dating from 1912, the two-tube 640 m long Rendsburg Canal Tunnel, which opened in 1961, was the second underwater tunnel built in Germany for road traffic. Now it is the...

more
Issue 06/2013 Austria

Bosruck Tunnel: Redeveloping the existing Bore

A second bore was produced by drill+blast using the New Austrian Tunnelling Method (NATM) for the 5.5 km long, 2-lane Bosruck Tunnel on the A?9 motorway. It possesses 2 lanes. After being broken...

more
Issue 04/2017

Structural Fire Protection in the Strenger Tunnel

1 Introduction The Strenger Tunnel, which was built between 2000 and 2005 on the S16 Arlberg expressway, is roughly 5.8 km long and consists of two tubes. This road tunnel, which is located between...

more
Issue 06/2014

Rendsburg Canal Tunnel: Safe Drainage in Case of Emergency

As early as the tunnel planning stage, the infrastructure and installations have to be taken into consideration, which act in a preventive manner, i.e. that avoid critical incidents as far as...

more