Germany

New Ebensfeld-Erfurt Rail Route: Eierberge and Füllbach Tunnels

The 3,756 m long, twin-track Eierberge Tunnel was broken through at its south portal on August 29, 2011 following 14 months of construction. The tunnel is part of the new and upgraded Leipzig/Halle-Erfurt-Nuremberg route – a German Unity Transport project – 8.2/8.3 – involving a total investment of some 10 b. euros. The tunnel is the longest in the Bavarian section of the project.

The Eierberge Tunnel was driven in the southern third and from the north by drill+blast with shotcrete being used to secure the rock. In the process remarkable Jurassic geological formations came to light. A total...

Related articles:

Issue 2010-06 Germany

The two-track Eierberge Tunnel with a length of 3,756 m is a part of the new line between Ebensfeld and Leipzig (with a total of 22 tunnels, altogether 41 km long accounting for 38 % of the route). It...

more
Issue 2011-04 Germany

Work on producing 2 further tunnels on the 107 km long new rail route (NBS) between Ebensfeld and Erfurt with a designated speed of 300 km/h has begun. The route is part of the 500 km long new and...

more
Issue 2011-04 Germany

The 2-track Kulch Tunnel with a length of 1,331 m in the Lichtenfels district is part of the 107 km long new railway line (NBS) between Ebensfeld and Erfurt, (with altogether 22 tunnels with 41 km...

more
Issue 2011-07 Germany

The twin-track and 1,490?m long Fleckberg Tunnel located between the Silberberg (7,391?m) and Messenger (1,051?m) tunnels is part of the 107?km long new rail link between Ebensfeld and Leipzig with a...

more
Issue 2012-08 Germany

After the completion of the currently largest infrastructure programme in the Federal Republic of Germany, the German Unity Transport (VDE) Project No. 8, it will be possible to travel by train in...

more