Risk Management in Major Tunnelling Projects – Part 3

Creating Incentive Mechanisms for Integrated Project Delivery

Due to their organisational structure and contracts, conventional project delivery models reach their limits in complex large-scale construction projects. In this context, Integrated Project Delivery (IPD) is an alternative regarding a joint project realisation. A probabilistic determination and integral consideration of cost, schedule and risk is the basis for developing an appropriate incentive mechanism for IPA. These elements are linked, simulated and analysed using a digital project risk twin. The results are transparently available to all project partners. Through the set incentive mechanism, the goals of the participants are harmonised and individual risk potentials and dependencies become visible. Based on this, an incentive mechanism has to be designed that ensures a fair pain/gain distribution between the participants.

1 Project Delivery Models
1.1 Overview

A project delivery model consists of three components: the type of award, the contractor assignment form and the type of contract [1, pp. 64-65]. A distinction can be made between conventional project delivery models, which consist of an award and a contractor assignment form (e.g. sole contractor or general contractor), and a contract, which can be a unit price contract or a lump sum price contract. Integrated Project Delivery has a collaborative project structure, which leads to all participants acting in a “best-for-project” manner [2, p. 84]. This is supported by an incentive-based contract and should lead to a shared project success. Conventional project management is briefly explained in section 1.2 and IPD in section 1.3. Section 1.4 principally describes the implementation of IPD.

1 | Overview of project delivery models
Credit/Quelle: RiskConsult GmbH

1 | Overview of project delivery models
Credit/Quelle: RiskConsult GmbH

 

An overview of the most common project delivery models is given in Figure 1, where the parameters of project complexity, level of design/defined scope and risk allocation are listed first. These parameters influence the choice of project delivery and contract model.

In general, a distinction can be made between project delivery methods and contract models [3, p. 15–17]. Project delivery models are designed by the client – usually by engineers from a project management office. The choice of contract is a consequence of the previously chosen project delivery model. Legal experts are then consulted to draft the contract.

As an example (cf. Figure 1), the allocation of risk between the client and the contractor can be described by a ratio. For lump sum price contracts, the ratio is 0/100. The first figure represents the client’s share of the risk and the second figure is the contractor’s percentage share of the risk. The ratio of 0/100 thus states that the contractor assumes 100% of the risk under the lump sum price contract [4, p. 145].

An incentive contract (cost plus incentive fee) is used in IPD. In this form of contract, target cost is defined. If the final cost falls below the agreed target cost, the saving is shared between the two partners according to a contractually agreed ratio. If the target cost is exceeded, both partners share a malus. As a rule, a minimum and a maximum remuneration are also set [5, p. 110]. Beyond these limits, the client assumes 100% of the opportunities and dangers (risk) [6, pp. 232–233]. This incentive mechanism is negotiated individually for each project.

A hybrid form of incentive contract is the “fixed price incentive fee” model. Here – as in the “cost plus incentive fee” model – an incentive mechanism is defined, but there is a fixed cost component [7, p. 35]. The incentive mechanism from the target cost can be supplemented by other key performance indicators in target areas for schedules, quality, occupational safety and others.

1.2 Conventional Project Delivery Models

In Germany, unit price or lump sum price contracts are mostly used for conventional project delivery models [8, p. 12]. However, especially in complex construction projects, conventional project delivery models do not always achieve the desired results. Structural difficulties often arise as the required services cannot be fully specified in advance with a bill of quantities. Moreover, various disruptive factors can be identified: Inadequate assessment of requirements, uneconomical selection of participants, lack of risk management, strict separation of planning and execution, lack of cooperation and inadequate conflict resolution management.

To reduce these negative factors in planning and execution, innovative project delivery models have been developed in various countries [9, p. 21–31].

1.3 Integrated Project Delivery

The Integrated Project Delivery (IPD) model originating from the USA has also been used in Germany since 2018 [10, p. 63]. This innovative project delivery model relies on increased integration of all project participants [2,  p. 80].

The core principles of IPA can be summarised as follows [9, p. 125, 11, p. 149]:

Early Contractor Involvement (ECI), to integrate expertise as early as possible

Financial transparency through the use of the Open Book method, joint decisions and development of project objectives

Early identification and quantification of risks

Shared risk management and risk bearing incl. compensation based on the success of the project (incentive contract)

Exchange of knowledge and information using technical resources

Equal representation in the project team and unanimous decisions by the key participants

Mutual and comprehensive exclusion of liability and avoidance of legal disputes by means of internal conflict resolution processes

2 Implementation of Integrated Project Delivery

An adaptation of the IPD for complex large-scale projects in road construction is the delivery model “Partnership Project Delivery (PPA)” [4, p. 152, 11, p. 149-150] and in railway construction the delivery model “Partnership Rail Model”. This essentially has the core principles listed in section 1.3 and is subdivided into four further sub-models. The sub-model PPA3+ (Partnership Project Delivery 3+) is initiated after a feasibility study as of HOAI service phases 3/4. It can be divided into five elements (A-E) [12, p. 6-7]. As shown in Figure 2, these can also be assigned to the service phases.

2 | Implementation of the IPD with the German PPA 3+ model
Credit/Quelle: RiskConsult GmbH

2 | Implementation of the IPD with the German PPA 3+ model
Credit/Quelle: RiskConsult GmbH

 

In this article, the implementation of the PPA3+ model is considered. Here, elements A (integral design) and B (overall execution preparation) are explicitly considered. During the research project DigiPeC (Digital Performance Contracting Competence Center), these elements were developed into a detailed process (see Figure 2):

1. Initiation of the partnership model

2. Selection of the project partners (award)

3. Start of the partnership model

4. Optimisation of planning and preparation of a cost and risk analysis

5. Development of the incentive mechanism, agreement on target cost and schedule

6. Joint contract design

 

The aim of the DigiPeC research project is to improve the efficiency and cost-effectiveness of public procurement for complex large-scale projects in the long term. The research project is intended to contribute to aligning the target systems of the client and contractor through incentive-based contracts and risk-based control to ensure that major projects can sustainably be procured and operated more successfully [13].

Part 1 and part 2 of this publication series already dealt with step 4 (optimisation of planning and risk analysis) of the detailed process according to DigiPeC. The structure of a project risk twin was explained, which offers an integral and probabilistic view of cost, schedules and risks [14, 15]. This enables both the client and all contractors to validate the costs transparently and to agree on target costs for the project. In the execution phase, accounting is carried out with the Open Book method [16, p. 667]. The review of execution costs is accompanied by an external expert (auditor/construction expert). The digital project risk twin is continuously updated; thus, deviations from the agreed target cost can be identified at an early stage, e.g. through scenario analyses. Based on the validated and agreed results of the project risk twin, the incentive mechanism for determining the target cost and target schedule is developed.

3 Development of Probabilistic Incentive Mechanisms
3.1 Basic Principles

This chapter deals with the determination of target costs. A model for defining the incentive-driven target dates is developed analogous to the project risk twin. The target cost (Fig. 3) is determined based on the direct project cost.

3 | Incentive mechanism with covered direct project cost
Credit/Quelle: RiskConsult GmbH

3 | Incentive mechanism with covered direct project cost
Credit/Quelle: RiskConsult GmbH

 

The overhead and the base profit are set as percentages. The target cost should be chosen at a realistic level that can be reduced. The target cost also includes the risks identified and assessed by both contracting parties [5, p. 116]. The target profit is the profit that the contractor would receive for exactly achieving the target cost. If the direct project cost at completion correspond to the target cost, the contractor’s profit corresponds exactly to the target profit. The sum of target cost, overhead and profit results in the target price from the client’s point of view. Depending on the actual performance, the contractor can achieve an additional bonus on top of the target profit if the target cost is undercut; conversely, a malus is also possible.

3.2 Example 1: Incentive Mechanism With Covered Direct Project Cost

Figure 3 depicts an incentive mechanism. The horizontal axis shows the potential final costs for the client, the vertical axis the compensation of the contractor. The light blue dashed line shows the owner/contractor share-ratio. In this example, the ratio was set at 50/50 across all areas. This means that if the target cost is undercut or exceeded, the deviation is split equally between the two partners.

Figure 3 (1) shows the target cost and the target profit, which were defined in the contract.

Figure 3 (2) shows a scenario at the end of the project in which the final cost is lower than the agreed target cost. Due to the lower final cost, the green dashed line shifts to the left. This can be achieved by, for example, increased efficiency, use of new, innovative construction methods, etc. In this case, the contractor generates a bonus of 50% of the savings in addition to the target profit (increased profit). The remaining 50% of the savings goes to the client. Figure 3 (3) represents a negative scenario. In this case, the target cost is exceeded, resulting in a reduction of profit. The final cost (yellow dashed line) shifts to the right in the horizontal axis. This can be caused, for example, by poor work performance, errors in the execution of the work, construction defects, etc. In this case, the Contractor is charged a penalty of 50% of the overrun of the target cost. The Client also has to pay 50% of the overrun.

Figure 3 (4) shows a further increase in final cost. In this scenario, the contractor would not make a profit at the end of the project and loses part of his overhead. If this happens, there is no incentive left for the contractor. In the worst case, only the production cost is covered.

4 | Incentive mechanism with additional depiction of the probabilities for gain and pain
Credit/Quelle: RiskConsult GmbH

4 | Incentive mechanism with additional depiction of the probabilities for gain and pain
Credit/Quelle: RiskConsult GmbH

 

In addition to the model in Figure 3, Figure 4 shows the distribution density of the potential final cost from the project risk twin. The distribution contains all uncertainties from base cost, risks and escalation (future price increase) based on the direct project cost.

In the example in Figure 4, an underrun probability of 50% (P50) is selected for the target costs. This means that the target cost will be reduced with a probability of 50%.

The decisive factor for an agreement between the client and the contractor on the target cost is the potential of the contractor to reduce the target cost and thus generate an additional profit. The success of an IPD depends largely on the correct choice of the target cost. This must be done individually on the basis of the results of the probabilistic risk analysis and the integral consideration of cost and schedules.

Figure 4 on the bottom shows the evaluation from the contractor’s perspective of a potential gain or loss (pain) at the selected target cost of P50. The probabilities for the pain/gain potentials in this example are as follows:

A) 15% probability that the target profit and the full bonus (maximum profit) will be achieved.

B) 35% probability that the target profit and a portion of the bonus will be paid. In total, there is a 50% probability (blue dashed line) that a profit above the target profit will be achieved.

C) 30% probability that the target profit will not be achieved and only part of the profit can be generated

D) 15% probability that no profit is achieved and a share of the overhead is deducted as a malus

E) 5% probability that the profit and the overhead are completely lost and only the direct project cost is reimbursed

3.3 Example 2: Incentive Mechanism With Covered Overhead and Direct Project Cost

5 | Incentive mechanism with covered direct project cost and overhead
Credit/Quelle: RiskConsult GmbH

5 | Incentive mechanism with covered direct project cost and overhead
Credit/Quelle: RiskConsult GmbH

 

Another modelling for an incentive mechanism is shown in Figure 5. Analogue to the direct project cost (cf. Fig. 4), the overhead is always remunerated here. These two cost components are therefore not taken into account in the malus system. In contrast to Figure 3 and Figure 4, an individual remuneration formula is defined for each remuneration area in order to create a greater incentive:

a) The potential final cost is below the defined target cost, thus the profit ceiling is reached. All further savings are retained 100% by the client.

b) The final cost is below the defined target cost in the range of the bonus. The distribution of the bonus is 25% for the client and 75% for the contractor. This division of the bonus is intended to create a higher incentive for the contractor to stay below the target cost.

c) If the potential final cost is above the target cost in the range of reduced profit, the profit for the parties involved is reduced. The split for exceeding the target cost is 50/50.

d) Once the contractor’s profit is wiped out by the malus, the client is responsible for all further cost.

6 | Incentive mechanism of a sample tunnel construction project using the professional risk software RIAAT
Credit/Quelle: RiskConsult GmbH

6 | Incentive mechanism of a sample tunnel construction project using the professional risk software RIAAT
Credit/Quelle: RiskConsult GmbH

 

Figure 6 shows the implementation of the model from Figure 5 for an exemplary tunnel project. In the bottom right-hand corner, one can see that the blue distribution “Remuneration of the contractor” never becomes negative, so that the client always covers the overhead. The probability is 10% that no profit can be made. The target profit of 20.7 million euros is shown at P50 and corresponds to 5% of the target cost of production at P50 (414.1 million euros). The profit ceiling of 41.4 million euros is reached with a probability of 20%.

6 Summary

This third part of the article series “Risk Management in Major Tunnelling Projects” shows how the incentive mechanism for the IPD can be designed by means of a digital project risk twin and a probabilistic risk analysis. An essential factor for the agreement of the incentive mechanism as well as for the success of the project is a transparent determination and a common understanding of the project cost. An incentive mechanism should be developed individually for each project with the aim of promoting the incentive for all parties to work collaboratively.

Thus, by means of probabilistic considerations, it is possible to indicate probabilities for the scenarios of undercutting or exceeding the target cost and therefore make the chances of additional profit or loss assessable. This analysis is continuously updated during construction.

References/ Literatur
 
[1] M. Budau und D. Mayer, „Analyse und Darstellung wesentlicher Bestandteile von Projektabwicklungsformen im Bauwesen“ in 30. BBB-Assistententreffen 2019 in Karlsruhe: Fachkongress der wissenschaftlichen Mitarbeiter Bauwirtschaft, Baubetrieb, Bauverfahrenstechnik : 10.–12. Juli 2019 : Institut für Technologie und Management im Baubetrieb (TMB), Karlsruher Institut für Technologie (KIT), S. Haghsheno, K. Lennerts und S. Gentes, Hg., Karlsruhe: KIT Scientific Publishing, 2019, S. 54–68.
[2] S. Haghsheno, C. Baier, A. Schilling Miguel, P. Talmon und M. R.-D. Budau, „Integrated Project Delivery (IPD) – Ein neues Projektabwicklungsmodell für komplexe Bauvorhaben“, Bauwirtschaft, Nr. 2, S. 80–93, 2020.
[3] S. Riemann, Ansätze zur Nutzung des Unternehmer-Know-hows bei öffentlich finanzierten Infrastrukturprojekten in Deutschland mit besonderem Fokus auf der Planungsphase. Zugl.: Kassel, Univ., Diss., 2014. Kassel: Univ.-Press, 2014.
[4] S. Riemann und P. Sander, „Partnerschaftliches Arbeiten in der Bauwirtschaft“, Bauwirtschaft, Jg. 4, S. 143–154, 2019.
[5] P. Sander und M. Spiegl, „Risikomanagement als Erfolgsfaktor für anreizbasierte Bauverträge“ in Kooperative Vertragsmodelle und baubetriebliche Lösungsansätze – Ist Deutschland reif für Alternativen?, P. Schwerdtner, Hg., 1 Aufl., Braunschweig: Institut für Bauwirtschaft und Baubetrieb der Technischen Universität Braunschweig, 2019, S. 100–122.
[6] P. Sander und S. Riemann, „Partnerschaftliches Arbeiten bei Straßenbauprojekten in Deutschland“, bau aktuell, Jg. 11, Nr. 6, S. 231–239, 2020.
[7] P. Sander, M. Spiegl und J. Reilly, „Incentive-Bases Project Delivery with Fixed Price Incentive Fee Contracts“ in Rapid Excavation and Tunneling Conference (2019, Chicago, IL), Rapid Excavation and Tunneling Conference, Hg., Chicago, 2019, S. 34–45.
[8] S. Scharpf und A. Al Khadadji, „Kooperative Vertragsmodelle – Vergleichende Analyse des GMP- und des Allianz-Vertrages“ in Tagungsband zum 29. BBB-Assistententreffen – Fachkongress der wissenschaftlichen Mitarbeiter der Bereiche Bauwirtschaft, Baubetrieb und Bauverfahrenstechnik: Beiträge zum 29. BBB-Assistententreffen vom 06. bis 08. Juni 2018 in Braunschweig, P. Schwerdtner und T. Kessel, Hg., Zentrum für Bau- und Infrastrukturmanagement, S. 11–22.
[9] J. Warda, Die Realisierbarkeit von Allianzverträgen im deutschen Vertragsrecht: Eine rechtsvergleichende Untersuchung am Beispiel von Project Partnering, Project Alliancing und Integrated Project Delivery, 1. Aufl. Baden-Baden: Nomos Verlagsgesellschaft, 2020.
[10] S. Haghsheno, C. Baier, M. R.-D. Budau, A. Schilling Miguel, P. Talmon und L. Frantz, „Strukturierungsansatz für das Modell der Integrierten Projektabwicklung (IPA)/Structuring approach for Integrated Project Delivery“, Bauingenieur, Jg. 97, Nr. 03, S. 63–76, 2022, doi: 10.37544/0005-6650-2022-03-47.
[11] S. Riemann, „Partnerschaftliche Projektabwicklung im Bundesfernstraßenbau aus Sicht des Auftraggebers“ in Bd. 34, Vorträge zum Deutschen Bautechnik-Tag am 23. und 24. April 2015 in Düsseldorf, Deutscher Beton- und Bautechnik-Verein e.V., Hg., Berlin: Frauenhofer IRB, 2015, S. 149–150.
[12] M. Sundermeier, P. Beidersandwisch, H. Kleinwächter und T. Rehfeld, „Partnerschaftliche Projektabwicklung für die Schienenverkehrsinfrastruktur“, Berlin, 2019. [Online]. Verfügbar unter: https://www.bau.tu-berlin.de/fileadmin/a3631/pdf/Partnerschaftsmodell_Schiene_-_Kurzbericht__TU_Berlin_.pdf.
[13] dtecbw.de, DigiPeC – Digital Performance Contracting Competence Center: Risikobasierte Steuerung komplexer Projekte öffentlicher Auftraggeber mit „Digital Twins“ und „Smart Contracts“. [Online]. Verfügbar unter: https://dtecbw.de/home/forschung/unibw-m/projekt-digipec.
[14] P. Sander, S. C. Becker und K. Nübel, „Risk Management in Major Tunnelling Projects – Part 1: Basics and Success Factors“, tunnel, Nr. 2, S. 18–27, 2021.
[15] P. Sander, S. C. Becker, M. Lammers, K. Uphoff, R. Brodehl und A. van Droogenbroeck, „Digital Project Risk Twin – Application for the Construction of U5 East, Hamburg“, tunnel, Nr. 6, S. 20–29, 2021.
[16] G. Girmscheid, Projektabwicklung in der Bauwirtschaft – prozessorientiert. Berlin, Heidelberg: Springer Berlin Heidelberg, 2016.
1 This publication is supported by dtec.bw – Centre for Digitalisation and Technology Research of the University of the Bundeswehr [DigiPeC – Digital Perfomance Contracting Competence Center].
x

Related articles:

Issue 2020-06 Austria

Brenner Base Tunnel: BBT SE Terminates Construction Contract with ARGE H51 Pfons–Brenner

The BBT SE’s Perspective: “The final refusal to carry out the contractually agreed works and the subsequent loss of trust has unfortunately forced us to dissolve the contract with ARGE H51. Even...

more
Austria

Brenner Base Tunnel: BBT SE Terminates Construction Contract with ARGE H51 Pfons–Brenner

The BBT SE’s Perspective: “The final refusal to carry out the contractually agreed works and the subsequent loss of trust has unfortunately forced us to dissolve the contract with ARGE H51. Even...

more
Issue 2021-06 Risk Management in Major Tunnelling Projects – Part 2

Digital Project Risk Twin – Application for the Construction of U5 East, Hamburg

1 Introduction In the first part, „Risk Management in Major Tunnelling Projects – Part 1: Fundamentals and Success Factors“, the relevance of transparent cost and risk management for large...

more
Issue 2021-02

Risk Management in Major Tunnelling Projects – Part 1: Basics and Success Factors

1 Introduction In Germany, the Reform Commission on the Construction of Major Projects already presented its final report in 2015 [1]. A central recommendation is the implementation of systematic...

more
Issue 2015-06 Lebanon

CREG signed two Gripper TBMs to Beirut Water Supply Tunnel Project

On July 17, 2015, the Italian construction contractor CMC and TBM manufacturer CREG signed a procurement contract of supplying two Gripper TBMs with a diameter of 3.5 m each for the LB-Greater Beirut...

more